Pilgrim news at nuclear.com
Pilgrim news

nuclear.com Nuclear Power other Entergy plants other Mark 1 BWRs Radiation Spent fuel Bookstore Gift Shop About nuclear.com
Pilgrim FAQs

NRC has a performance indicator and inspection finding matrix webpage for Pilgrim.


Pilgrim news

March 28, 2011

Pilgrim Watch sees Fukushima accidents as relevant to Pilgrim license renewal, Post-Hearing Memorandum filed with ASLB

June 30, 2007

New this week from NRC Public Document Room

* [2007-06-30] Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station ML071410455 2007-06-28 719 05000293 DPR-035 2007-06-28 2007-06-29 ML071410438+ Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station Docket No. 50-293 Entergy Nuclear Operations U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulatio

* [2007-06-30] Transmittal Letter to M. Kansler Re: Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station ML071410036 2007-06-28 6 05000293 DPR-035 2007-06-28 2007-06-29 ML071410438+ June 28, 2007 Mr. Michael Kansler President Entergy Nuclear Operations, Inc. 440 Hamilton Avenue White Plains, NY 10601-1839 SUBJECT: SAFETY EVALUATION REPORT RELATED TO THE LICENSE RENEWAL OF PILGRIM NUC

* [2007-06-30] Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station ML071410438 2007-06-29 ML071410036+ ML071410455+ FNWEBNAVIGATE=1.0 SYSTEMTYPE=MEZZANINE DOCUMENTID=071410438 STARTPAGE=1 LIBRARYNAME= ML_adams^hqntad01

* [2007-06-27] 2007/06/18- Pilgrim - Hearing File Index ML071700042 2007-06-18 10 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13790 2007-06-18 2007-06-26 2007-06-19 ML071700056+ ATTACHMENT 1: PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL HEARING FILE AND MANDATORY DISCLOSURES Supplement 7: June 18, 2007 HF# Accession Number Document Date

* [2007-06-27] Press Release-I-07-036 - NRC Names New Senior Resident Inspector at Pilgrim Nuclear Power Plant ML071760529 2007-06-21 1 05000293 Press Release-I-07-036 2007-06-21 2007-06-26 NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs, Region I 475 Allendale Road, King of Prussia, Pa. www.nrc.gov No. I-07-036 June 21, 2007 Contact: Diane Screnci, 610/337-5330 E-mail

* [2007-06-27] 2007/06/19- Pilgrim - Letter to Administrative Judges (Hearing File on Pilgrim Nuclear Power Station) and Hearing File Index ML071700056 2007-06-26 ML071700036+ ML071700042+ FNWEBNAVIGATE=1.0 SYSTEMTYPE=MEZZANINE DOCUMENTID=071700056 STARTPAGE=1 LIBRARYNAME= ML_adams^hqntad01

* [2007-06-27] 2007/06/28- Pilgrim - Letter to Administrative Judges (Pilgrim Nuclear Power Station LR) ML071700036 2007-06-18 7 2007-06-18 2007-06-26 2007-06-19 ML071700056+ June 18, 2007 Richard F. Cole Paul B. Abramson Administrative Judge Administrative Judge Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop: T-3F23 Mail Stop: T-3F23 U.S. Nuclear Regu

June 23, 2007

New this week from NRC Public Document Room

* [2007-06-19] 01/16/2007 Budget Presentation,"Town of Plymouth Fiscal Year 2008 Budget Primer." ML071570049 2007-01-16 16 05000293 TAC MD3698 2007-01-16 2007-06-18 Swn of Plym.outh Fi scal Ye ar 2008 Budget Prnmer Budget Presentation January 16, 2007 Budget Development *Objectives- - Goal setting/performance based budget initiatives initiated with the FY 2007 budget - Matchin

* [2007-06-19] CR-PNP-2003-01618 with Supporting Report (with Redacted Notes) 1st Page for Inspector ML071560251 2003-04-27 17 05000293 IR 03-0283 CR-PNP-2003-01618 2003-04-27 2007-06-18 Ente#g-y Approved By: Closed By: Pace,Raymond M - I 2' I\ Current Due Date: 05/05/2003 Initial Due Date: 05/05/2003 '\ CA Type: CORRECTIVE ACTION Plant Constraint: RFO14D- DRN DWN VSSL CA Descript

* [2007-06-19] E-MAIL (NPA-PD) FW: Letter to MA State Historic Preservation Officer ML071570063 2007-05-09 17 05000293 TAC MD3698 2007-05-09 2007-06-18 I Alicia Williamson - FW: Letter to MA State Historic Preservation Officer Page 1à Alicia Williamson - FW: Letter to MA State Historic Preservation Officer Page 1 I From: "Mogolesko, Fred" To:

* [2007-06-19] E-MAIL (NPA-PD) FW: MACCS2 Input Files for Sensitive Cases in ER ML071570059 2007-05-04 16 05000293 TAC MD3698 2007-05-04 2007-06-18 I Alicia Williamson - FW: MACCS2 input files for sensitivity cases in ER I Page I1I I Alicia..Will.amson....FW:. MAC. CS..inpu. f....l....s . fo sen......si ....... iv.i..ty ...... cases in ER Page 1 From: "Mogoles

* [2007-06-19] E-MAIL (NPA-PD) Re: MACCS2 Input files for Sensitive Cases ML071570052 2007-05-02 3 05000293 TAC MD3698 2007-05-02 2007-06-18 Alicia Williamson - RE: MACCS2 input files for sensitivity cases Page 1 Alicia Williamson - -RE: MACCS2 input files for sensitivity cases Page A From: "Mogolesko, Fred" To: Date

* [2007-06-19] E-MAIL: (NPA-PD) 5/10 Phone Conference ML071580985 2007-05-10 4 05000293 TAC MC9669 TAC MD3698 2007-05-10 2007-06-18 Page 1 of I Perry Buckberg - 5/10 Phone conference From: To: Date: Subject: Perry Buckberg Edward Sanchez 5/10/2007 3:41:19 PM 5/10 Phone conference Please see the attached summary of today's conference

* [2007-06-19] E-MAIL: (NPA-PD) Amendment 16 reply ML071580958 2007-05-08 2 05000293 TAC MD3698 2007-05-08 2007-06-18 Page 1 of 1 Perry Buckberg - Amendment 16 reply From: Perry Buckberg To: Edward Sanchez Date: 5/8/2007 9:53:06 AM Subject: Amendment 16 reply Ed, Please review and pass on this preliminary response to Amendment 16.

* [2007-06-19] E-MAIL: (NPA-PD) Amendment 16 ML071580976 2007-05-31 2 05000293 TAC MD3698 2007-05-31 2007-06-18 Page 1 of I Perry Buckberg - Amendment 16 From: "Mogolesko, Fred" To: "Perry Buckberg" Date: 5/31/2007 11:02:12 AM Subject: Amendment 16 CC: "Bethay, Stephen"

* [2007-06-19] E-MAIL: (NPA-PD) Cost Benefit Equation Terms ML071570118 2007-05-24 3 05000293 TAC MD3698 2007-05-24 2007-06-18 iRort Palla - Cost Benefit Equation Terms ..... Page 1 From: Robert Palla To: jojones@sandia.gov Date: 05/24/2007 7:10:00 AM Subject: Cost Benefit Equation Terms Joe - I am not sure whether I had provided you with

* [2007-06-19] E-MAIL: (NPA-PD) Entergy Efficiency Article ML071560479 2007-05-03 35 05000293 TAC MD3698 2007-05-03 2007-06-18 I Alicia Williamson - Energy Efficiency Article Page I1,1 . .. Alicia ..... William son ... - Energy...... Efiie c Article.. Page..-<:. ,*.. ................. . .. . . .... . 11. I From: "Broom, Katie"

* [2007-06-19] E-MAIL: (NPA-PD) Entergy LRA Letter Part 1 of 2 ML071640328 2007-05-01 34 05000293 DPR-035 TAC MD3698 2007-05-01 2007-06-18 Page 1 of 1 Perry Buckberg - Entergy LRA letter part I of 2 From: "Sanchez, Edward" To: Date: 5/1/2007 7:22:38 PM Subject: Entergy LRA letter part 1 of 2 Perry, Attached

* [2007-06-19] E-mail: (NPA-PD) FW: MACCS2 Input Files for Sensitivity Cases in ER ML071570037 2007-05-04 15 05000293 TAC MD3698 2007-05-04 2007-06-18 FW: MACCS2 input files for sensitivity cases in ER Page I of I Robert Palla - FW: MACCS2 input files for sensitivity cases in ER From: "Mogolesko, Fred" To: "Alicia Williamson" ,

* [2007-06-19] E-MAIL: (NPA-PD) Fwd: Pilgrim Waste Discussion ML071560466 2007-05-02 5 05000293 TAC MD3698 2007-05-02 2007-06-18 AlcaWlimo-Fd igrmWseDsuso ae1 I Alicia Williamson - Fwd: Pilgrim Waste Discussion Page 11 From: Jessie Muir To: Alicia Williamson Date: 05/02/2007 12:45:26 PM Subject: Fwd: Pilgrim Waste Discussion Alicia, I receiv

* [2007-06-19] E-MAIL: (NPA-PD) LRA Amendment 17 ML071640345 2007-05-17 53 05000293 DPR-035 TAC MD3698 2007-05-17 2007-06-18 I Perry"B ucl"kbe'rg - LRA Amendment 17 Page i~j From: To: Date: Subject: "Sanchez, Edward" "Perry Buckberg" 5/17/2007 5:07:50 PM LRA Amendment 17 Perry, Attached is a

* [2007-06-19] E-MAIL: (NPA-PD) LRA Letter Part 2 ML071640339 2007-05-01 35 05000293 TAC MD3698 2007-05-01 2007-06-18 Page 1 of 1 Perry Buckberg - LRA letter part 2 From: "Sanchez, Edward" To: Date: 5/1/2007 7:23:37 PM Subject: LRA letter part 2 Perry, Attached is part 2 of 2 of the 01 resp

* [2007-06-19] E-MAIL: (NPA-PD) LRA question ML071580988 2007-05-10 3 05000293 TAC MD3698 2007-05-10 2007-06-18 IPerry Buckbe-rg_-_LRA quesfio Pa6 1n Pfage l_1l From: "Sanchez, Edward" To: "Perry Buckberg" Date: 5/10/2007 12:45:31 PM Subject: LRA question Perry, Attached is a page from A

* [2007-06-19] E-MAIL: (NPA-PD) Pilgrim Amendment 17 of 5/17/2007 ML071640347 2007-05-18 55 05000293 TAC MD3698 2007-05-18 2007-06-18 Page 1 of 1 Perry Buckberg - Pilgrim Amendment 17 of 5/17/2007 From: Perry Buckberg To: Pilgrim Staff Date: 5/18/2007 7:02:29 AM Subject: Pilgrim Amendment 17 of 5/17/2007 Gentlemen, The attached letter was e-maile

* [2007-06-19] E-MAIL: (NPA-PD) Pilgrim Amendment ML071640342 2007-05-01 68 05000293 TAC MD3698 2007-05-01 2007-06-18 I Perry BuckberQ - PiIQrim Amendment I - PaQe1 From: To: Naeem IQBAL Date: Subject: Perry Buckberg Christopher Sydnor; Dan Hoang; James Davis; Lambros Lois; Matthew Mitchell; 5/1/2007 9:20:11 PM Pilgrim Amendment T

* [2007-06-19] E-MAIL: (NPA-PD) RE: 5/10 Phone Conference ML071580981 2007-05-10 2 05000293 DPR-035 TAC MD3698 2007-05-10 2007-06-18 Page 1 of 1 Perry Buckberg - RE: 5/10 Phone conference From: "Sanchez, Edward" To: "Perry Buckberg" Date: 5/10/2007 4:48:20 PM Subject: RE: 5/10 Phone conference Perry,

* [2007-06-19] E-MAIL: (NPA-PD) RE: Cost Benefit Equation Terms [Response from N. Bixler, Sandia] ML071570122 2007-05-24 2 05000293 TAC MD3698 2007-05-24 2007-06-18 R-ob-eiiPalla-aRE: Cost Benefit Equation Terms ___Page1ll From: "Bixler, Nathan E" To: "Robert Palla" Date: 05/24/2007 12:09:08 PM Subject: RE: Cost Benefit Equation Terms Bob, W

* [2007-06-19] E-MAIL: (NPA-PD) RE: Cost Benefit Equation Terms ML071570124 2007-05-24 2 05000293 TAC MD3698 2007-05-24 2007-06-18 I..... -- .. -- .- -. - - I I Kobert Palla - RE: Cost Benefit Equation Terms Pa ge1 From: Robert Palla To: Nathan E Bixler Date: 05/24/2007 2:44:25 PM Subject: RE: Cost Benefit Equation Terms Nate - this is covered

* [2007-06-19] E-MAIL: (NPA-PD) Re: Fw: Pilgrim Fluence RAIs ML071640324 2007-05-07 3 05000293 TAC MD3698 2007-05-07 2007-06-18 Per Bcbeg- RE_:FW_:Pilgrim FluenceRA Page-1 From: "Sanchez, Edward" To: "Perry Buckberg" Date: 5/7/2007 4:46:05 PM Subject: RE: FW: Pilgrim Fluence RAIs Perry, Thanks. I've pas

* [2007-06-19] E-MAIL: (NPA-PD) Re: Fwd: Pilgrim Waste Discussion ML071560469 2007-05-03 3 05000293 TAC MD3698 2007-05-03 2007-06-18 I Alicia Williamson - Re: Fwd: Pilgrim Waste Discussion Pa~ae I I I AliciaW.ll.a son...e:..w . .... lgrim.. .. W aste....Discuss....on........ ¦ v ...... I From: Jessie Muir To: Alicia Williamson Date: 05/03/2007 7

* [2007-06-19] E-MAIL: (NPA-PD) Re: MACCS2 Input Files for Sensitivity Cases ML071570036 2007-05-04 2 05000293 TAC MD3698 2007-05-04 2007-06-18 Robert..Pall - RE: MACCS2 input files for sensitivity casesPage From: Alicia Williamson To: Fred Mogolesko Date: 05/04/2007 1:31:03 PM Subject: RE: MACCS2 input files for sensitivity cases Fred, Please email the fi

* [2007-06-19] E-MAIL: (NPA-PD) RE: Revised Phone Conference Letter (5/10) ML071580965 2007-05-14 2 05000293 TAC MD3698 2007-05-14 2007-06-18 Page 1 of I Perry Buckberg - RE: Revised Phone Conference Letter (5/10) From: To: Date: Subject: "Ford, Bryan" Perry Buckberg 5/14/2007 4:18:56 PM RE: Revised Phone Conference L

* [2007-06-19] E-MAIL: (NPA-PD) Revised Phone Conference Letter (5/10) ML071580962 2007-05-14 5 05000293 TAC MD3698 2007-05-14 2007-06-18 Page 1 of 1 Perry Buckberg - Revised Phone Conference Letter (5/10) From: Perry Buckberg To: Bryan Ford Date: 5/14/2007 3:55:39 PM Subject: Revised Phone Conference Letter (5/10) CC: Edward Sanchez Bryan, I receive

* [2007-06-19] Redacted Page (1) from: Follow Up to CR-PNP-2005-05471 - Outstanding Questions (License Document) ML071560232 2007-06-04 1 05000293 CR-PNP-2005-05471 2007-06-04 2007-06-18 Follow-Up to CR-PNP-2005-0547 1 Procedure 8.E. 19' Issue Condition Description: A concern was identified during the NRC 9/18/2006 through 9/22/2006 inspection for license t-enewal concerning the refuel floor

* [2007-06-16] 2007/06/08- Pilgrim - Entergy's Motion for Summary Disposition of Pilgrim Watch Contention 1 ML071640454 2007-06-08 95 05000293 DPR-035 50-293-LR ASLBP 06-848-02-LR RAS 13760 NUREG-1801, Vol. 1, Rev. 1 2007-06-08 2007-06-15 2007-06-08 /3760 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board Panel June 8, 2007 DOCKETED USNRC

June 16, 2007

New this week from NRC Public Document Room

* [2007-06-16] Summary of Conference Call on May 10, 2007, with Entergy Nuclear Operations, Inc., Regarding the Pilgrim License Renewal Application (TAC No. MC9669) ML071310069 2007-06-08 7 05000293 2007-06-08 2007-06-15 June 8, 2007 LICENSEE: Entergy Nuclear Operations, Inc. FACILITY: Pilgrim Nuclear Power Station SUBJECT: SUMMARY OF TELEPHONE CONFERENCE CALL HELD ON MAY 10, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NU

* [2007-06-15] 2007/03/05- Pilgrim - Email from Eric Epstein to David R. Lewis in re: seeking copy of bridge number for conference ML070650581 2007-03-05 2 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13142 2007-03-05 2007-06-14 2007-03-05 From: Eric Epstein To: "Lewis, David R." Date: Mon, Mar 5, 2007 4:46 PM Subject: Re: Teleconference I r

* [2007-06-15] 2007/03/05-E-mail from David R. Lewis to Administrative Judge Young regarding conference call scheduled for 03/08/07 ML070650631 2007-03-05 2 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13144 2007-03-05 2007-06-14 2007-03-05 From: "Lewis, David R." To: "Ann Young" , , , "HearingDocket"

* [2007-06-15] 2007/05/30- Pilgrim - NRC Staff motion for extension of time to reply to Entergy's motion for summary judgment ML071650255 2007-05-30 5 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13710 2007-05-30 2007-06-14 2007-05-31 DOCKETED USNRC May 30,2007 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD May 31,2007 (4:08pm) In the Matter of Entergy Nu

* [2007-06-15] NRC Receipt of Pilgrim Nuclear Power Station, Response To Generic Letter 2003-01 "Control Room Habitability" (TAC No. MB9840) ML071090262 2007-06-07 5 05000293 DPR-035 GL-03-001 TAC MB9840 2007-06-07 2007-06-14 June 7, 2007 Mr. Michael Kansler President Entergy Nuclear Operations, Inc. 440 Hamilton Avenue White Plains, NY 10601 SUBJECT: NRC RECEIPT OF PILGRIM NUCLEAR POWER STATION, RESPONSE TO GENERIC LE

* [2007-06-14] 2007/06/05- Pilgrim - Entergy's Sixth Supplemental Disclosure ML071630395 2007-06-05 5 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13747 2007-06-05 2007-06-13 2007-06-06 ~RfV~$~ j~7t4%7 June 5, 2007 J1UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of Entergy Nuclear Generation

* [2007-06-14] 4/20/2007 - Legal Motion for Filing for Commonwealth of Massachusetts v. NRC Case Nos. 07-1482 and 07-1483 ML071560312 2007-04-20 122 05000271 05000293 07-1482 07-1483 2007-04-20 2007-06-13 2300 N Sreet NW Tel 202.683.0 Pillsbury Washington, DC 20037-1122 Fax 202.663.8007 W in th ro p mw yww,,-, r=, .com Shaw Pittman April 20, 2007 Paul A. Gaulder Phone: 202.663.8304 paul.gaukler@pillsbu

June 9, 2007

New this week from NRC Public Document Room

* [2007-06-09] 2007/05/31-Pilgrim - Email from Susan Uttal to Administrative Judges and Parties re: Pilgrim Watch response to Entergy's Motion for Summary Judgment ML071510163 2007-05-31 3 05000293 50-293-LR ASLBP 06-848-02 RAS 13704 2007-05-31 2007-06-08 2007-05-31 From: To: Date: Subject: Susan Uttal Pilgrim 11/06 Thu, May 31, 2007 9:46 AM Supplemental Information concerning Staff motion to extend time. Dear Administrative Judges and Parti

* [2007-06-09] 2007/06/01- Pilgrim - Letters to Administrative Judges (Pilgrim Nuclear Power Station) ML071550020 2007-06-01 1 05000293 06-848-02-LR 50-293-LR RAS 13715 2007-06-01 2007-06-08 2007-06-01 June 1, 2007 Administrative Judge Administrative Judge Ann Marshall Young, Chair Paul B. Abramson Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop T-3 F

* [2007-06-09] 5/14/2007 - Commonwealth of Massachusetts, Petitioner v. USNRC Regarding Reply to Entergy's Opposition to Motion to Hold Petitions for Review in Abeyance; Nos. 07-1482 and 07-1483 ML071440215 2007-05-14 7 05000271 05000293 07-1482 07-1483 2007-05-14 2007-06-08 UNITED STATES COURT OF APPEALS FOR THE FIRST CIRCUIT ) COMMONWEALTH OF ) MASSACHUSETTS, ) ) Petitioner, ) ) v. ) Nos. 07-1482 and ,) 07-1483 UNITED STATES NUCLEAR REGULATORY ) COMMISSION and the UNITE

* [2007-06-09] Pilgrim - Supplemental Follow-Up Response to NRC Generic Letter 2003-01 ML071510191 2007-05-22 2 05000293 DPR-035 2.07.050 GL-03-001 2007-05-22 2007-06-08 Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment May 22, 2007 U.S. Nuclear Regulatory Commission A

* [2007-06-07] 2007/05/15- Pilgrim - Declaration of Thomas L. Sowdon in Support of Entergy's Motion for Summary Disposition of Pilgrim Watch Contention 3 ML071440332 2007-05-15 58 05000293 DPR-035 50-293-LR ASLBP 06-848-02-LR RAS 13684 2007-05-15 2007-06-06 2007-05-18 ML071440314+ May 15, 2007 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of Entergy Nuclear Generati

* [2007-06-07] 2007/05/16 - Pilgrim - Declaration of Kevin R. O'Kula ML071440354 2007-05-16 99 05000293 DPR-035 50-293-LR ASLBP 06-848-02-LR RAS 13684 2007-05-16 2007-06-06 2007-05-18 ML071440314+ May 16, 2007 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )) Entergy Nuclear Gener

* [2007-06-07] 2007/05/16- Pilgrim - Declaration of Fred J. Mogolesko in Support of Entergy's Motion for Summary Disposition of Pilgrim Watch Contention 3 ML071440333 2007-05-16 7 05000293 DPR-035 50-293-LR ASLBP 06-848-02-LR RAS 13684 2007-05-16 2007-06-06 2007-05-18 ML071440314+ May 16, 2007 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )) Entergy Nuclear Gener

* [2007-06-07] 2007/05/17- Pilgrim - Entergy's Motion for Summary Disposition of Pilgrim Watch Contention 3 ML071440321 2007-05-17 34 05000293 DPR-035 50-293-LR ASLBP 06-848-02-LR RAS 13684 2007-05-17 2007-06-06 2007-05-18 ML071440314+ May 17,2007 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION DOCKETED Before the Atomic Safety and Licensing Board-Panel USNRC May 18, 2007 (8:00am)

* [2007-06-07] 2007/05/17- Pilgrim - Statement of Material Facts submitted by counsel for Entergy ML071440325 2007-05-17 10 05000293 DPR-035 50-293-LR ASLBP 06-848-02-LR RAS 13684 2007-05-17 2007-06-06 2007-05-18 ML071440314+ May 17, 2007 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board Panel In the Matter of ) ¥) Entergy Nucle

* [2007-06-07] 2007/05/28- Pilgrim - Pilgrim Watch's Reply to Entergy's Opposition to Pilgrim Watch Request to Extend Time to Respond to Summary Disposition of Pilgrim Watch Contention 3 ML071570380 2007-05-28 5 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13720 2007-05-28 2007-06-06 2007-06-06 ,-RA! DOCKETED USNRC UNITED STATES OF AMERICA June 6,2007 (9:30am) NUCLEAR REGULATORY COMMISSION OFFICE OF SECRETARY RULEMAKINGS AND Before theAtomic Safety and Licensing Boar

* [2007-06-07] 2007/06/05-LB Order (Granting Request for Extension) ML071560454 2007-06-05 4 05000293 06-848-02-LR 50-293-LR RAS 13718 2007-06-05 2007-06-06 2007-06-05 1Order (Granting Request for Extension) (May 30, 2007) [hereinafter May 30, 2007, Order]; Request by Pilgrim Watch for Extension of Time to Reply to Entergy's Motion for Summary Dis

* [2007-06-07] Pilgrim - Tech Spec Pages for Amendment 228 Re: Single Control Rod Withdrawal Allowances ML071560542 2007-04-25 12 05000293 DPR-035 tac mc9018 2007-04-25 2007-06-06 ML071220402+ -3- B. Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 22q are hereby incorporated in the license. The licensee shall operate the

* [2007-06-07] Pilgrim, License Renewal Application Amendment 17 ML071550310 2007-05-17 51 05000293 DPR-035 2.07.029 TAC MC9669 2007-05-17 2007-06-06 SEntergy Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment May 17, 2007 U.S. Nuclear Regulatory Co

* [2007-06-07] 2007/05/17- Pilgrim - Entergy's Motion for Summary Disposition of Pilgrim Watch Contention 3 ML071440314 2007-06-06 ML071440321+ ML071440325+ ML071440332+ ML071440333+ ML071440354+ FNWEBNAVIGATE=1.0 SYSTEMTYPE=MEZZANINE DOCUMENTID=071440314 STARTPAGE=1 LIBRARYNAME= ML_adams^hqntad01

* [2007-06-07] Pilgrim - Issuance of License Amendment 228 Re: Single Control Rod Withdrawal Allowances (TAC No. MC9018) ML071220402 2007-06-06 ML070740419+ ML071560542+ FNWEBNAVIGATE=1.0 SYSTEMTYPE=MEZZANINE DOCUMENTID=071220402 STARTPAGE=1 LIBRARYNAME= ML_adams^hqntad01

* [2007-06-05] 2007/05/18 - Pilgrim - Letter To Administrative Judges (Pilgrim Nuclear Power Station) ML071510064 2007-05-18 13 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13660 2007-05-18 2007-06-04 2007-05-18 May 18, 2007 Administrative Judge Administrative Judge Richard F. Cole Paul B. Abramson Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail St

* [2007-06-05] 2007/05/22- Pilgrim - Notice of Withdrawal of Molly H. Bartlett ML071520174 2007-05-22 3 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13711 2007-05-22 2007-06-04 2007-05-23 P\AT 137i! DOCKETED USNRC May 23, 2007 (8:00 am) OFFICE OF SECRETARY UNITED STATES OF AMERICA RULEMAKINGS AND NUCLEAR REGULATORY COMMISSION ADJUDICATIONS STAFF BEFORE THE ATOM

* [2007-06-05] 2007/05/22-Pilgrim - Notice of Appearance of Mary Elizabeth Lampert ML071520168 2007-05-22 3 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13712 2007-05-22 2007-06-04 2007-05-22 àAs 13 f) / ), UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the matter of Entergy Corporation Pikrim Nuclear Power St

* [2007-06-05] 2007/05/22-Pilgrim - Request by Pilgrim Watch for Extension of Time to Reply to Entergy's Motion for Summary Disposition ML071520175 2007-05-22 3 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13713 2007-05-22 2007-06-04 2007-05-22 Vfa- 5 13 7/13 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the matter of Entergy Corporation Pilgrim Nuclear Power S

* [2007-06-05] 2007/05/24- Pilgrim - Entergy's Opposition to Pilgrim Watch Request to Extend Time to Respond to Summary Disposition of Pilgrim Watch Contention 3 ML071500299 2007-05-24 6 05000293 DPR-035 50-293-LR ASLBP 06-848-02-LR RAS 13696 2007-05-24 2007-06-04 2007-05-24 May 24, 2007 DOCKETED USNRC UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION May 24, 2007 (4:12pm) OFFICE OF SECRETARY Before the Atomic Safety and Licensing Boa

* [2007-06-05] Pilgrim Nuclear Power Station - License Renewal Application Amendment 16 ML071280251 2007-05-01 65 05000293 DPR-035 2.07.027 TAC MC9669 2007-05-01 2007-06-04 Entergy Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment May 1,2007 U.S. Nuclear Regulatory Commi

* [2007-06-05] Pilgrim Nuclear Power Station, Technical Specifications, Limiting Conditions for Operation ML071430305 2007-04-25 1 05000293 DPR-035 tac mc9018 2007-04-25 2007-06-04 TABLE OF CONTENTS LIMITING CONDITIONS FOR OPERATION SURVEILLANCE REQUIREMENTS 3.6 PRIMARY SYSTEM BOUNDARY 4.6 3/4.6-1 A. Thermal and Pressurization Limitations A 3/4.6-1 B. Coolant Chemistry B 3/4.6-3 C. Co

June 2, 2007

New this week from NRC Public Document Room

* [2007-06-02] Pilgrim - Special Report - TS Table 3.2.F, Inoperable Main Stack High Range Radiation Monitor ML071430192 2007-05-16 3 05000293 DPR-035 2.07.052 2007-05-16 2007-06-01 SEntergy Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Diretor, Nudear Assessment May 16, 2007 U.S. Nuclear Regulatory Commission Att

* [2007-06-02] Pilgrim, Third Ten-Year ISI Interval Relief Request, PRR-42, Examinations of Component Welds with Less than Essentially 100% Examination Coverage ML071430188 2007-05-16 2 05000293 DPR-035 2.07.051 2007-05-16 2007-06-01 - En tergy Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nudear Assessment May 16, 2007 U.S. Nuclear Regulatory Commission A

* [2007-06-01] 2007/05/30-LB Order (Granting Request for Extension) ML071500416 2007-05-30 5 05000293 06-848-02-LR 50-293-LR RAS 13702 2007-05-30 2007-05-31 2007-05-30 1Request by Pilgrim Watch for Extension of Time to Reply to Entergy's Motion for Summary Disposition (May 22, 2007); Entergy Motion for Summary Disposition of Pilgrim Watch Contenti

* [2007-06-01] LER 07-001-00 for Pilgrim Regarding Primary Containment Isolations Following a Manual Reactor Scram ML071420092 2007-05-16 6 05000293 DPR-035 2.07.049 LER 07-001-00 2007-05-16 2007-05-31 'à Entergy Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Kevin H. Bronson Site Vice President May 16, 2007 U.S. Nuclear Regulatory Commiss

* [2007-05-30] Pilgrim Nuclear Power Station - Withdrawal of a Relief Request (TAC No. MD2477) ML071410032 2007-05-22 4 05000293 DPR-035 TAC MD2477 2007-05-22 2007-05-29 May 22, 2007 Mr. Michael Kansler President Entergy Nuclear Operations, Inc. 440 Hamilton Avenue White Plains, NY 10601 SUBJECT: PILGRIM NUCLEAR POWER STATION - WITHDRAWAL OF A RELIEF REQUEST (TAC NO. MD2477

May 26, 2007

New this week from NRC Public Document Room

* [2007-05-26] Pilgrim Nuclear Power Station - Response To Bulletin (BL) 2005-02 "Emergency Preparedness And Response Actions For Security-Based Events" (TAC No. MC7859) ML071300366 2007-05-18 6 05000293 DPR-035 BL-05-002 TAC MD7859 2007-05-18 2007-05-25 May 18, 2007 Mr. Michael R. Kansler President Entergy Nuclear Operations, Inc. 440 Hamilton Avenue White Plains, NY 10601 SUBJECT: PILGRIM NUCLEAR POWER STATION - RESPONSE TO BULLETIN (BL) 2005-02

* [2007-05-25] 04/17/2007 Summary of Annual Assessment Meeting With Entergy Nuclear Operations, Inc., Regarding the NRC's Assessment of the Safety Performance of Pilgrim Nuclear for the Calendar Year 2006 ML071370142 2007-05-18 3 05000293 2007-05-18 2007-05-24 May 18, 2007 MEETING SUMMARY LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC. FACILITY: PILGRIM NUCLEAR POWER STATION SUBJECT: SUMMARY OF APRIL 17, 2007 ANNUAL ASSESSMENT MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC. On April 17, a

* [2007-05-25] Feedback Form for Pilgrim Annual Assessment Meeting 2006-07 ML071370151 2007-05-18 1 05000293 MN 07-012 2007-05-18 2007-05-24 PUBLIC MEETING FEEDBACK SUMMARY MN No: 07-012 Meeting Date: 4/17/2007 Meeting Location: Hilton Garden Inn, Plymouth, MA Meeting Purpose/Licensee: Pilgrim 2006 Annual Assessment Was the overall public perception of t

* [2007-05-25] Pilgrim Nuclear Power Station - Correction To Technical Specifications (TAC MC9018) ML071340143 2007-05-17 4 05000293 DPR-035 tac mc9018 2007-05-17 2007-05-24 May 17, 2007 Mr. Michael Kansler President Entergy Nuclear Operations, Inc. 440 Hamilton Avenue White Plains, NY 10601 SUBJECT: PILGRIM NUCLEAR POWER STATION - CORRECTION TO AMENDMENT NO. 228 - SINGLE CONTR

* [2007-05-25] Pilgrim, Core Operating Limits Report, Revision 26 (Cycle 17) ML071360197 2007-05-09 46 05000293 DPR-035 2.07.048 2007-05-09 2007-05-24 'r-1- Entergy Nuclear Operations, Inc. Pilgrim Station 600 Rocky Hill Road Plymouth, MA 02360 May 9, 2007 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 SUBJEC

* [2007-05-24] Final QA/Related Forms (Folder 1) ML071340135 2007-02-20 10 05000293 DPR-035 50-293/07-301 ES-201 ES-201-1 50-293/07-301 2007-02-20 2007-05-23 Task Description (Reference) Chief Examiner's initials 1. 2. Examination administration date confirmed (C.1 .a; C.2.a and b) NRC examiners and facility contact assigned (C.l

* [2007-05-24] Pilgrim - Annual Radiological Environmental Operating Report for January 1 through December 31, 2006 ML071350482 2007-05-09 97 05000293 DPR-035 2.07.047 2007-05-09 2007-05-23 mm"EnheW Entergy Nuclear Operations, Inc. Pilgrim Station 600 Rocky Hill Road Plymouth, MA 02360 May 9, 2007 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 SUBJECT:

* [2007-05-24] Pilgrim Radioactive Effluent Release Report for January 1 through December 31, 2006 ML071350484 2007-05-09 93 05000293 DPR-035 2.07.046 2007-05-09 2007-05-23 EnteiW Entergy Nuclear Operations, Inc. Pilgrim Station 600 Rocky Hill Road Plymouth, MA 02360 May 9, 2007 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 SUBJECT: E

* [2007-05-22] Pilgrim - Additional Information Concerning Revised Request for Authorization Under the Provision of 10 CFR 50.55a(a)(3)(i) for Modification of Core Shroud Stabilizer Assemblies ML071310083 2007-05-03 13 05000293 DPR-035 2.07.045 TAC MD4918 2007-05-03 2007-05-21 Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 May 3, 2007 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 205

* [2007-05-22] Pilgrim Nuclear Power Station - Issuance of Amendment RE: Adoption of Technical Specification Task Force (TSTF) Change TSTF-372, "The Addition of Limiting Condition for Operation (LCO) 3.0.8 on the Inoperability of Snubbers" (TAC No. MD3579) ML070871165 2007-05-14 25 05000293 DPR-035 TAC MD3579 2007-05-14 2007-05-21 May 14, 2007 Mr. Michael R. Kansler President Entergy Nuclear Operations, Inc. 440 Hamilton Avenue White Plains, NY 10601 SUBJECT: PILGRIM NUCLEAR POWER STATION - ISSUANCE OF AMENDMENT RE: ADOPTION OF TECHN

May 19, 2007

New this week from NRC Public Document Room

* [2007-05-19] 2007/05/08- Pilgrim - Entergy's Fifth Supplemental Disclosure. ML071350505 2007-05-08 7 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13607 2007-05-08 2007-05-18 2007-05-08 )~ ~ Z LO~9 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board May 8, 2007 DOCKETED USNRC May 8, 2007 (2:21pm) OFFICE OF SECRE

* [2007-05-19] E-MAIL: (NPA-PD) Entergy EFH Comment References - Pilgrim. ML071280811 2007-04-20 2 05000293 DPR-035 TAC MD3698 2007-04-20 2007-05-18 Alic~a Wdharnson-Re: Entergy EFH Comment References Page 1~I Alicia Williamson - Re: Entergy EFH Comment References Page 1 From: To: Date: Subject: Alicia Williamson Jacob Scheffer 04/20/2007 8:10:06 AM Re:

* [2007-05-19] E-MAIL: (NPA-PD) Entergy EFH Comment References doc - Pilgrim. ML071280814 2007-04-13 3 05000293 DPR-035 TAC MD3698 2007-04-13 2007-05-18 Acia Williamson - EntergyEFH comment references.doc .... . . ... .. Pa From: Alicia Williamson To: bford@entergy.com Date: 04/13/2007 12:19:10 PM Subject: Entergy EFH comment references.doc See attached. Al

* [2007-05-19] E-mail: (NPA-PD) Entergy EFH Comment References2 - Pilgrim. ML071290120 2007-04-19 68 05000293 DPR-035 TAC MD3698 2007-04-19 2007-05-18 ...... .... ... .. ............................. . ....... Entergy_..................................Co m m en t. . ....... ............ Referen ces.. . ........................ .P age............. 1.......

* [2007-05-19] E-mail: (NPA-PD) Link to Rutgers Slides on WRF Calcs - Pilgrim. ML071280766 2007-04-26 6 05000293 TAC MD3698 2007-04-26 2007-05-18 Natasha Greene - Link to Rutgers Slides on WRF Caics From: Robert Palla To: Natasha Greene Date: 4/26/2007 2:40:17 PM Subject: Link to Rutgers Slides on WRF Calcs Mark Lilly provided me the following link, which mi

* [2007-05-19] LTR-07-0346 - Nancy M. Oates re Annual Town Meeting on 03/10/2007on Articles 38 & 39, Pilgrim Aging Management Plan & Pilgrim Plume Transport Model. ML071370655 2007-03-10 3 05000293 LTR-07-0346 2007-03-10 2007-05-18 r ¥ OFFICE OF THE SECRETARY ¥ CORRESPONDENCE CONTROL TICKET Date Printed: Mlay 16, 2007 16:57 PAPER NUMBER: ACTION OFFICE: AUTHOR: AFFILIATION: ADDRESSEE: SUBJECT: ACTION: DISTRIBUTION: LETTER DATE: ACKNOWLEDGED S

* [2007-05-19] Pilgrim, License Renewal Comments on Draft Safety Evaluation Report, Dated March 2007. ML071380190 2007-03-28 17 05000293 DPR-035 2.07.028 TAC MC9669 2007-03-28 2007-05-18 EnteW Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment March 28, 2007 Mr. Michael Lesar Chief, Ru

* [2007-05-19] Pilgrim, Response to NRC Generic Letter 2007-01, "Inaccessible or Underground Power Cable Failures that Disable Accident Mitigation Systems or Cause Plant Transients." ML071300361 2007-05-03 3 05000293 DPR-035 2.07.034 GL-07-001 2007-05-03 2007-05-18 Entergy Nuclear Operations, Inc. : *ePilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Kevin H. Bronson Site Vice President May 3, 2007 U.S. Nuclear Regulatory Commission Attn: Do

* [2007-05-19] E-MAIL: (PD) Annulus drain line buckets. ML071200197 2007-04-02 3 05000293 TAC MD3698 2007-04-02 2007-05-18 Page 1 of 1 Perry Buckberg - Annulus drain line buckets. From: "Ford, Bryan" To: , "Perry Buckberg" Date: 4/2/2007 3:34:49 PM Subject: Annulus drain line buckets

* [2007-05-19] E-MAIL: (PD) Buried Pipes and Tanks Inspection Program - Pilgrim. ML071240467 2007-04-25 2 05000293 TAC MD3698 2007-04-25 2007-05-18 Page 1 of I Perry Buckberg - Buried Pipes and Tanks Inspection Program- Pilgrim From: "Mary Lampert" To: Date: 4/25/2007 10:09 AM Subject: Buried Pipes and Tanks Inspection

* [2007-05-19] E-MAIL: (PD) Conference Call Record 4/2/2007. ML071200188 2007-04-03 6 05000293 DPR-035 TAC MD3698 2007-04-03 2007-05-18 Page 1 of 1 Perry Buckberg - Conference Call Record 4/2/2007 From: Perry Buckberg To: Doug Ellis Date: 4/3/2007 10:16:27 AM Subject: Conference Call Record 4/2/2007 CC: Bryan Ford; Robert Schaaf Doug, Pleas

* [2007-05-19] E-MAIL: (PD) Copy of PNPS LRA Annual Update Letter. ML071200179 2007-04-18 4 05000293 DPR-035 TAC MD3698 2007-04-18 2007-05-18 Page 1 of 1 Perry Buckberg - copy of PNPS LRA Annual Update letter From: "Sanchez, Edward" To: Date: 4/18/2007 5:37:39 PM Subject: copy of PNPS LRA Annual Update lett

* [2007-05-19] E-MAIL: (PD) Fw: Revised Drywell UT Table and Annulus Drain VT-2 Datasheets. ML071200177 2007-04-02 24 05000293 DPR-035 TAC MD3698 2007-04-02 2007-05-18 Page 1 of 1 Perry Buckberg - FW: REVISED DRYWELL UT TABLE AND ANNULUS DRAIN VT-2 DATASHEETS From: "Ford, Bryan" To: , "Perry Buckberg" Date: 4/2/2007 11:1

* [2007-05-19] E-MAIL: (PD) Re: Conference Call Record 4/2/2007. ML071200187 2007-04-12 3 05000293 TAC MD3698 2007-04-12 2007-05-18 Page 1 of I Perry Buckberg - RE: Conference Call Record 4/2/2007 From: "Ford, Bryan" To: "Perry Buckberg" Date: 4/12/2007 8:20:18 AM Subject: RE: Conference Call Record 4/2/2007

* [2007-05-19] E-MAIL: (PD) Re: PNPS Request. ML071240473 2007-04-26 3 05000293 TAC MD3698 2007-04-26 2007-05-18 Page 1 of 2 Perry Buckberg - Re: PNPS request From: "Mary Lampert" To: "Perry Buckberg" Date: 4/26/2007 11:20 AM Subject: Re: PNPS request Thank-you ----- Original Message

* [2007-05-19] (NPA-PD) Letter to Mary Lampert from the Commonwealth of Massachusetts Executive Office of Heath and Human Services, Department of Public Health, Regarding Child Heath Statistics. ML071290155 2006-05-09 13 05000293 TAC MD3698 2006-05-09 2007-05-18 The Commonwealth of Massachusetts Executive Office of Health and Human Services Department of Public Health 250 Washington Street, Boston, MA 02108-4619 MITT ROMNEY GOVERNOR KERRY HEALEY LIEUTENANT GOVERNOR TIMOTHY

* [2007-05-19] E-mail (NPA-PD) Additional Info/References: Sea Breeze Journal Article. ML071290387 2007-04-25 35 05000293 TAC MD3698 2007-04-25 2007-05-18 I1 Robert Palla - Additional Info/References Page 1 ii From: To: Date: Subject: Robert Palla Natasha Greene 04/25/2007 2:26:04 PM Additional Info/References see attached CC: jojones @ sandia.gov 1; c:\temp\GWJ00001

* [2007-05-19] E-MAIL (NPA-PD) Paper Abstract. ML071290298 2007-04-24 4 05000293 TAC MD3698 2007-04-24 2007-05-18 Robert Palla - Paper Abstract Page I From: Robert Palla To: Natasha Greene Date: 04/24/2007 2:52:54 PM Subject: Paper Abstract I came across this, as well as some papers (actually just abstracts) by Jen Thorpe and

* [2007-05-17] Pilgrim, Revised Request for Authorization under Provision of 10 CFR 50.55a(a)(3)(i) for Modification of Core Shroud Stabilizer Assemblies. ML071280519 2007-04-29 18 05000293 DPR-035 2.07.042 TAC M91305 TAC MD4918 2007-04-29 2007-05-16 Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment April 29, 2007 U.S. Nuclear Regulator

* [2007-05-15] Annual Assessment Letter EOC 2006 - Pilgrim Station (IR 05000293-07-001). ML070610612 2007-03-02 6 2007-03-02 2007-05-14

* [2007-05-15] IR 05000293-06-007; Entergy Nuclear Operations; 09/18/2006 - 12/07/2006; Pilgrim Nuclear Power Station; Inspection of the Scoping of Non-Safety Systems and the Proposed Aging Management Procedures for the Application for Renewed License. ML070750055 2007-03-15 39 2007-03-15 2007-05-14

* [2007-05-15] 01/23/2007 Summary of Conference Call with Entergy Nuclear Operations, Inc., Re: Pilgrim License Renewal Application to Discuss Ut of Drywell Shell, Water on Torus Room Floor & to Request Documentation for Periodic Testing of Fire Water System Equipment. ML070300793 2007-02-16 6 2007-02-16 2007-05-14

* [2007-05-15] 01/24/2007 Summary of Meeting with Pilgrim on the Draft Supplemental Environmental Impact Statement Regarding Pilgrim License Renewal Review. ML070540205 2007-03-01 14 2007-03-01 2007-05-14

* [2007-05-15] 04/17/2007, Meeting with Entergy Nuclear Operations, Inc., to Discuss NRC's Assessment of the Safety Performance of the Pilgrim Nuclear Power Station for Calendar Year 2006. ML070920459 2007-03-30 6 2007-03-30 2007-05-14

* [2007-05-15] 2007/02/15- Pilgrim - Updated Hearing File ML070540189 2007-02-15 20 2007-02-15 2007-05-14 2007-02-16

* [2007-05-15] 2007/02/22-Comment (24) submitted by Pilgrim Watch, Mary Lampert on Proposed Rules PR-50, PR-72, PR-73, regarding Power Reactor Security Requirements. ML070540299 2007-02-22 10 2007-02-22 2007-05-14 2007-02-22

* [2007-05-15] 2007/03/01- Pilgrim - Hearing File Update - Pilgrim Nuclear Power Station ML070610055 2007-03-01 1 2007-03-01 2007-05-14

* [2007-05-15] 2007/03/01-Safety Evaluation Report With Open Items Related to the License Renewal of Pilgrim Nuclear Power Station. ML070600798 2007-03-01 800 2007-03-01 2007-05-14

* [2007-05-15] 2007/03/01-Transmittal Ltr - Safety Evaluation Report With Open Items Related To The License Renewal Of Pilgrim Nuclear Power Station. ML070510236 2007-03-01 3 2007-03-01 2007-05-14

* [2007-05-15] 2007/03/06- Pilgrim - Letter to Judge Cole from S. Uttal, OGC providing (CD) version of Safety Evaluation Report with Open items. ML070730191 2007-03-06 1 2007-03-06 2007-05-14 2007-03-07

* [2007-05-15] 2007/03/13-Comment (35) submitted by Edward and Charlotte Russell Supporting Massachusetts Attorney General's PRM-51-10 re Spent Fuel at the Pilgrim. ML070730345 2007-03-13 2 2007-03-13 2007-05-14 2007-03-14

* [2007-05-15] 2007/03/15- Pilgrim - Entergy's Third Supplemental Disclosure. ML070800217 2007-03-15 5 2007-03-15 2007-05-14 2007-03-16

* [2007-05-15] 2007/03/19- Pilgrim - Updated Hearing File for Pilgrim Nuclear Power Station ML070780108 2007-03-19 22 2007-03-19 2007-05-14 2007-03-19

* [2007-05-15] 2007/04/02- Pilgrim - Notice of Withdrawal for Molly L. Barkman ML070930427 2007-04-02 3 2007-04-02 2007-05-14

* [2007-05-15] ACRS Review of the Pilgrim Nuclear Plant Station Renewal Application - Safety Evaluation Report. ML070640252 2007-03-06 6 2007-03-06 2007-05-14

* [2007-05-15] Attachments to Pilgrim Draft Environmental Impact Statement Afternoon Meeting Transcripts. ML070600309 2007-01-24 8 2007-01-24 2007-05-14

* [2007-05-15] Comment (10) of Robert W. Varney on Behalf of United States Environmental Protection Agency, Region 1 regarding Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants Supplement 29 regarding Pilgrim Nuclear Power Station. ML070660135 2007-02-28 10 2007-02-28 2007-05-14

* [2007-05-15] Comment (11) of Pine duBois on Behalf of Jones River Watershed Association on NRC's NUREG-1437, Supplement 29 Draft Report Regarding Pilgrim Nuclear Power Station. ML070660273 2007-02-28 9 2007-02-28 2007-05-14

* [2007-05-15] Comment (14) of Diana L. Woebcke Opposing Application Renewal for Pilgrim Nuclear Power Station. ML070660293 2007-02-28 4 2007-02-28 2007-05-14

* [2007-05-15] Comment (15) of Robert S. Knorr on the Draft Supplemental Environmental Impact Statement on the Pilgrim Nuclear Power Station located in Plymouth Massachusetts (NUREG-1437, Supplement 29). ML070660326 2007-02-28 3 2007-02-28 2007-05-14

* [2007-05-15] Comment (16) of Stephen J. Bethay, on Behalf of Entergy Nuclear Operations, Inc., on NUREG-1437, Supplement 29, Regarding Generic Environmental Impact Statement for License Renewal of Pilgrim Nuclear Power Station. ML070660079 2007-02-27 46 2007-02-27 2007-05-14

* [2007-05-15] Comment (17) of Mary Osborn Opposing Relicensing of Pilgrim Nuclear Power Plant (NUREG-1437, Suppl. 29). ML070660059 2007-02-27 41 2007-02-27 2007-05-14

* [2007-05-15] Comment (4) of Mary Lampert on Behalf of Pilgrim Watch regarding Draft NUREG-1437, Supplement 29. ML070470406 2007-02-14 3 2007-02-14 2007-05-14

* [2007-05-15] Comment (6) of Rebecca Chin Opposing Re-Licensing of Pilgrim Nuclear Plant in 2008. ML070660114 2007-02-23 8 2007-02-23 2007-05-14

* [2007-05-15] Comment (7) of Lilias Cingolani Opposing Re-Licensing of Pilgrim Nuclear Plant in 2008. ML070660117 2007-02-25 4 2007-02-25 2007-05-14

* [2007-05-15] Comment (8) of Millie Morrison Opposing Relicensing of Pilgrim Nuclear Power Station. ML070660122 2007-02-27 2 2007-02-27 2007-05-14

* [2007-05-15] Comments (9) of Diane Curran and Matthew Brock on Behalf of Massachusetts Attorney General Martha Coakley Opposing Draft Supplemental 29 to Generic EIS for License Renewal of Pilgrim Nuclear Power Plant. ML070660133 2007-02-28 5 2007-02-28 2007-05-14

* [2007-05-15] E-MAIL: (PD) Pilgrim Meeting Handouts. ML070680351 2007-02-07 2 2007-02-07 2007-05-14

* [2007-05-15] E-MAIL: (PD) Re: Pilgrim SEIS. ML070680341 2007-02-15 3 2007-02-15 2007-05-14

* [2007-05-15] FOIA/PA-2006-0159 - Pilgrim Nuclear Power Station "force-on-force" inspection in 2005, all communications & records; Emergency Plan, 1-06 proposal by Entergy Nuclear to amend staffing requirements, all communications & records ML060870081 2006-03-27 4 2006-03-27 2007-05-14 ML063420311+

* [2007-05-15] GE-NE-000-0064-9392-R2-NP, "Pilgrim Unit 1, IGSCC Assessment of Shroud Repair X-750 Component Other Than the Replacement Upper Support Assembly and Tie Rod Nut." ML070870134 2007-03-21 8 2007-03-21 2007-05-14

* [2007-05-15] GE-NE-0000-0061-6306-R4-NP, "Pilgrim Nuclear Power Station, Shroud Repair Replacement Upper Support Assembly-Stress Analysis Report." ML070930313 2007-03-14 38 2007-03-14 2007-05-14

* [2007-05-15] Letter Dated February 8, 2007 From Massachusetts Historical Commission, Brona Simon, Regarding Pilgrim Nuclear Power Station License Renewal Application, #RC36661. ML070510463 2007-02-08 1 2007-02-08 2007-05-14

* [2007-05-15] M070315 - Affirmation: I. SECY-07-0041 Motion for Reconsideration of Entergy Nuclear Vermont Yankee LLC & Entergy Nuclear Op Inc (Vermont Yankee Nuclear Power Station); Entergy Nuclear Generation Co. & Entergy Nuclear Op Inc (Pilgrim). ML070740694 2007-03-15 4 2007-03-15 2007-05-14

* [2007-05-15] Morning Report 1-2007-0008 - Pilgrim Manual Reactor Shutdown. ML070780524 2007-03-17 1 2007-03-17 2007-05-14

* [2007-05-15] MR-1-2007-0005 - Announced Management Changes for Pilgrim Station 03/09/2007. ML070680291 2007-03-09 1 2007-03-09 2007-05-14

* [2007-05-15] Operator Licensing Examination Approval (Pilgrim Nuclear Power Station). ML070520117 2007-02-20 3 2007-02-20 2007-05-14

* [2007-05-15] PD_Email from Fred Mogolesko, Entergy, dtd 8/22/06 re: Pilgrim AMP Review. ML070660279 2006-08-22 2 2006-08-22 2007-05-14

* [2007-05-15] PD_Email from Fred Mogolesko, Entergy, dtd 8/24/06 re: Pilgrim AMP Review. ML070670089 2006-08-24 4 2006-08-24 2007-05-14

* [2007-05-15] PD_Email from Fred Mogolesko, Entergy, dtd 8/28/06 re: Preparation for Region I Inspection at Pilgrim. ML070660056 2006-08-28 3 2006-08-28 2007-05-14

* [2007-05-15] Pilgrim - License Renewal Application Amendment 15. ML070790316 2007-03-13 11 2007-03-13 2007-05-14

* [2007-05-15] Pilgrim - Request for Authorization Under the Provision of 10 CFR 50.55a(a)(3)(i) for Modification of the Core Shroud Stabilizer Assemblies. ML070870132 2007-03-22 19 2007-03-22 2007-05-14

* [2007-05-15] Pilgrim Draft Environmental Impact Statement Public Meeting, January 24, 2007, Afternoon Transcript-Corrected. ML070530189 2007-01-24 97 2007-01-24 2007-05-14

* [2007-05-15] Pilgrim Draft Environmental Impact Statement Public Meeting, January 24, 2007, Evening Transcript-Corrected. ML070530185 2007-01-24 92 2007-01-24 2007-05-14

* [2007-05-15] Pilgrim License Renewal Application Amendment 14. ML070650350 2007-02-23 13 2007-02-23 2007-05-14

* [2007-05-15] Pilgrim Nuclear Power Station Hearing File Update. ML070930326 2007-03-01 1 2007-03-01 2007-05-14

* [2007-05-15] Pilgrim, Response to NRC Request for Additional Information Regarding Technical Specifications Changes for Single Control Rod Withdrawal Allowances. ML070650342 2007-02-23 4 2007-02-23 2007-05-14

* [2007-05-15] Request For Additional Information For The Review of The Pilgrim Nuclear Power Station License Renewal Application. ML070780058 2007-03-26 6 2007-03-26 2007-05-14

* [2007-05-15] Safety Evaluation Report with Open Items Related to the License Renewal of Pilgrim Nuclear Power Station. ML070600795 2007-05-14

* [2007-05-15] SRM-M070315-Affirmation Session: I. SECY-07-0041 - Motion for Reconsideration of Entergy Nuclear Vermont Yankee LLC & Entergy Nuclear Operations Inc. (Vermont Yankee); Entergy Nuclear Generation Company & Entergy Nuclear Operations Inc. (Pilgrim). ML070740655 2007-03-15 1 2007-03-15 2007-05-14

* [2007-05-15] Summary of Public Meetings on the Draft Supplemental Environmental Impact Statement Regarding the Pilgrim Nuclear Power Station, License Renewal Review. ML070590260 2007-05-14

* [2007-05-15] Supplemental Information In Support of Proposed Change to Applicability of Pilgrim's Pressure-Temperature Curves as Described in Technical Specification Figures 3.6.1, 3.6.2, and 3.6.3. ML070520355 2007-02-12 3 2007-02-12 2007-05-14

May 12, 2007

New this week from NRC Public Document Room

* [2007-05-12] NRC Exam Results Letter w/o Enclosures dtd 03/08/07. ML071020003 2007-03-08 3 05000293 DPR-035 2007-03-08 2007-05-11 March 8, 2007 Mr. Vincent Fallacaro Manager, Training and Development Chiltonville Training Center 46 Sandwich Road Plymouth, MA 02360 Dear Mr. Fallacaro: The purpose of this letter is to inform you of the individual

* [2007-05-12] IR 05000293-07-002; on 01/01/2007 - 03/31/2007; Pilgrim Nuclear Power Station; Integrated Inspection Report. ML071270525 2007-05-07 31 05000293 DPR-035 IR-07-002 2007-05-07 2007-05-11 UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 May 7, 2007 Mr. Kevin Bronson Site Vice President Entergy Nuclear Operations, Inc. Pilgrim Nuc

* [2007-05-10] Pilgrim Nuclear Power Station, Weld Filler and Welding Electrode Materials for Structural Weld Overlays Within the Scope of Pilgrim Relief Request, PRR-15. ML071210252 2007-04-21 11 05000293 DPR-035 2.07.040 PRR-15 TAC MD2663 2007-04-21 2007-05-09 F.WeW Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment April 21, 2007 U.S. Nuclear Regulat

* [2007-05-10] Pilgrim, Response to NRC Request for Additional Information Related to Repair of the Core Shroud Stabilizer Assemblies. ML071210250 2007-04-20 14 05000293 DPR-035 2.07.039 TAC MD4918 2007-04-20 2007-05-09 k&%EnteW Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment April 20, 2007 U.S. Nuclear Regulatory

* [2007-05-10] Pilgrim, Revision to Entergy Response to NRC Request for Additional Information Related to Repair of the Core Shroud Stabilizer Assemblies. ML071210254 2007-04-24 4 05000293 DPR-035 2.07.041 TAC MD4918 2007-04-24 2007-05-09 rEnteg Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment April 24, 2007 U.S. Nuclear Regulatory Co

* [2007-05-08] 3/22/2007 - Commonwealth of Massachusetts, Petitioner v. USNRC No. 07-1483. ML071080421 2007-03-22 81 05000293 DPR-035 07-1483 2007-03-22 2007-05-07 UNITED STATES COURT OF APPEALS FOR THE FIRST CIRCUIT No. 07-1483 COMMONWEALTH OF MASSACHUSETTS Petitioner V. UNITED STATES; UNITED STATES NUCLEAR REGULATORY COMMISSION Respondents CASE OPENING SCHEDULING NOTIC

* [2007-05-08] 2007/05/01- Pilgrim - Letter to Administrative Judges re Pilgrim Nucelar Power Station. ML071210147 2007-05-01 1 05000293 50-293-LR ASLBP 06-848-02-LR 2007-05-01 2007-05-07 2007-05-01 May 1, 2007 Administrative Judge Administrative Judge Ann Marshall Young, Chair Paul B. Abramson Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop T-3 F23 Ma

* [2007-05-08] Pilgrim - Draft - Outlines (Folder 2). ML070610437 2006-12-11 32 05000293 DPR-035 2006-12-11 2007-05-07 ES-401 BWR Examination Outline Form ES-407-1 Tier I. Emergency & Abnormal Plant Evolutions 2. Plant Systems Facilitv: Pilarim Date of Exam: 2/26/2007 Group KI K2 K3 K4 1 K5 I K6 AI A2 A3 [ A4 G* Total A2 G* Total 1 3

* [2007-05-08] Pilgrim, Draft - RO & SRO Written Exam (Folder 2). ML070610451 2006-12-11 199 05000293 DPR-035 2006-12-11 2007-05-07 ES-401 Sample Written Examination Form ES-401-5 Question Worksheet Examination Outline Cross-reference: Level RO SRO -4 Tier # 2 Group # 1 KIA # 203000 - RHWLPCI: Importance Rating 2.7 fnjection Mode - K2.03

* [2007-05-08] Pilgrim, Draft - Section A Operating Exam (Folder 2). ML070610466 2006-12-11 54 05000293 DPR-035 2006-12-11 2007-05-07 Appendix C Job Performance Measure Form ES-C-1 Worksheet 'L-., Facility: PILGRIM Task No.: 356-01 -07-004 Task Title: Perform a Short Form Heat Balance JPM No.: 2007 NRC JPM RO/SRO AI a WA Reference: 292008 KI 21 2.9

* [2007-05-08] Pilgrim, Draft - Section B Operating Exam (Folder 2). ML070610469 2006-12-11 101 05000293 DPR-035 NUREG-1021, Rev 9 2006-12-11 2007-05-07 ES-301 Control Room/ln-Plant Systems Outline Form ES-30 1 -2 P Facility: PNPS Date of Examination: 2 -26.07 Exam Level (circle one): RO / SRO(I) I SRO (U) Operating Test No.: 2007 NRC Control Room

* [2007-05-08] Pilgrim, Draft - Section C Operating Exam (Folder 2). ML070610472 2006-12-11 61 05000293 DPR-035 2006-12-11 2007-05-07 Scenario Event Description NRC Scenario 1 Facility: PILGRIM Scenario No.: 1 Op Test No.: 2007 NRC Examiners: Operators: initial Conditions: Power was lowered to 90% for control rod pattern adjustment which has been co

* [2007-05-08] Pilgrim, Final - Outlines (Folder 3). ML070820358 2007-02-20 20 05000293 DPR-035 2007-02-20 2007-05-07 ES-401 BWR Examination Outline Form ES-401-1 RO WA Category Points Group K1 K2 K3 K4 I K5 I K6 AI A2 A3 I A4 G* Total Tier 1. 1 4 3 4 5 2 1 I 9 & 2 1 2 2 1 8 1 1 NIA Emergency Abnormal Evolutions Totals N/A Plant Tier

* [2007-05-08] Pilgrim, Final - RO & SRO Written Examination with Answer Key (401-5 Format) (Folder 3). ML070820363 2007-02-20 200 05000293 DPR-035 2007-02-20 2007-05-07 ES-401 Sample Written Examination Form ES-401-5 b Question Worksheet Examination Outline Cross-reference: Level RO SRO .LJ Tier # 2 Group # 1 WA # 203000 - RHWLPCI: Injection Mode - K2.03 Importance Rating 2.7 Knowled

* [2007-05-08] Pilgrim, Final - Section A Operating Exam (Folder 3). ML070820392 2007-02-20 59 05000293 DPR-035 2007-02-20 2007-05-07 Appendix C Job Performance Measure Worksheet Form ES-C-1 Facility: PILGRIM Ll Task No.: 356-01-07-004 Task Title: Perform a Short Form Heat Balance JPM No.: 2007 NRC JPM RO & K/A Reference: 292008 K1.21 2.9 13.0 Exami

* [2007-05-08] Pilgrim, Final - Section B Operating Exam (Folder 3). ML070820405 2007-02-20 101 05000293 DPR-035 2007-02-20 2007-05-07 Appendix C Job Performance Measure Worksheet Form ES-C-1 Facility: PI LGRl M . . - Task No.: Task Title: Ooeration Of RClC To Inject To The JPM No.: 2007 NRC JPM - RPV RO/SRO S-2 WA Reference: A2.01 3.8 13.7 A3.01 3.5

* [2007-05-08] Pilgrim, Final - Section C Operating Exam (Folder 3). ML070820446 2007-02-20 44 05000293 DPR-035 2007-02-20 2007-05-07 Appendix D Scenario Outline Form ES-D-1 C - RO N - BOP I - BOP M - ALL Ód Control rod 22 - 31 drifts outward. (TS) (AOP) RFP ÕAÕ intermittent TBCCW leak, place RFP ÔBÕ in service. RWCU Pump ÕAÕ RBCCW Temp High, pump f

May 5, 2007

New this week from NRC Public Document Room

* [2007-05-05] Pilgrim, License Renewal Application Annual Update. ML071160152 2007-04-18 2 05000293 DPR-035 2.07.037 TAC MC9669 2007-04-18 2007-05-04 Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay Director, Nuclear Assessment April 18, 2007 U.S. Nuclear Regulatory Commissio

* [2007-05-04] Pilgrim FSEIS Reference - Nonradioactive Waste Information. ML071230016 2007-05-02 2 05000293 EN-EV-106 EN-EV-112 2007-05-02 2007-05-03 Pilgrim Station Nonradioactive Wastes Nonradioactive waste is produced from plant maintenance, cleaning and operational processes. The majority of the wastes generated consist of waste oil and oily debris,

* [2007-05-04] Pilgrim Nuclear Power Station, License Amendment, Issuance of Amendment Re: Single Control Rod Withdrawal Allowances (TAC No. MC9018). ML070740419 2007-04-25 14 05000293 DPR-035 tac mc9018 2007-04-25 2007-05-03 April 25, 2007 Mr. Michael Kansler President Entergy Nuclear Operations, Inc. 440 Hamilton Avenue White Plains, NY 10601 SUBJECT: PILGRIM NUCLEAR POWER STATION - ISSUANCE OF AMENDMENT RE: SINGLE CONTROL ROD

* [2007-05-02] 03/14-15/2007 Summary of Conference Calls With Entergy Nuclear Operations Inc., re: Pilgrim License Renewal Application, Pilgrim Request for Additional Information B.1.16.1, and Neutron Fluence. ML071030093 2007-05-01 6 05000293 DPR-035 TAC MC9669 2007-05-01 2007-05-01 May 1, 2007 LICENSEE: Entergy Nuclear Operations, Inc. FACILITY: Pilgrim Nuclear Power Station SUBJECT: SUMMARY OF CONFERENCE CALLS ON MARCH 14, 2007, AND MARCH 15, 2007, WITH ENTERGY NUCLEAR OPERATIONS, IN

* [2007-05-02] 2007/04/18- Pilgrim - Letter to Administrative Judges Updated Hearing File (Pilgrim Nuclear Power Station) ML071090040 2007-04-18 24 05000293 50-293-LR ASLBP 06-848-02 RAS 13524 2007-04-18 2007-05-01 April 18, 2007 Administrative Judge Administrative Judge Richard F. Cole Paul B. Abramson Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 M

* [2007-05-01] 2007/04/16- Pilgrim - Entergy's Fourth Supplemental Disclosure. ML071170260 2007-04-16 5 05000293 50-293-LR ASLBP 06-848-02-LR RAS 13469 2007-04-16 2007-04-30 2007-04-16 - R~-~ l3~#L~7 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board April 16, 2007 .DOCKETED USNRC April 16, 2007 (5:42pm) OFFIC

* [2007-05-01] 2007/04/18 - Pilgrim - Second Disclosure Statement by Pilgrim Watch. ML071170267 2007-04-18 5 05000293 50-293-LR ASLBP-06-848-02-LR LBP-06-23 RAS 13468 2007-04-18 2007-04-30 2007-04-26 If-3 r1(-Vb2 DOCKETED USNRC April 26, 2007 (1:13pm) OFFICE OF SECRETARY RULEMAKINGS AND UNITED STATES OF AMERICA ADJUDICATIONS STAFF NUCLEAR REGULATORY COMMISSION BE

* [2007-05-03] 2007/04/02- Pilgrim - Letter to Administrative Judges from D. Roth, OGC providing status of final SEIS or final SER. ML071010210 2007-04-02 1 50-293-LR ASLBP 06-848-02-LR RAS 10000 RAS 13367 2007-04-02 2007-05-02 2007-04-02 Administrative Judge Ann Marshall Young, Chair Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Administrative

April 28, 2007

New this week from NRC Public Document Room

* [2007-04-28] NRC Comments on Draft Licensee-Developed Exam (Written & Operating Tests) (Folder 2). ML070610425 2006-12-18 13 05000293 DPR-035 2006-12-18 2007-04-27 Comments on Pilgrim 2007 Exam Outline Comment GAJ BY GAJ GAJ Comment Resolution Use Scenarios 2,3 and 4; Scenario #1 Spare Agreed via TELCON 1211 4/06 Agreed via TELCON 12/14/06 Ensure ADMIN JPMs for SROs are more in

* [2007-04-28] Summary of Conference Calls on April 2, 2007, With Entergy Nuclear Operations, Inc., Regarding the Pilgrim License Renewal Application (TAC No. MC9669). ML071030053 2007-04-27 6 05000293 TAC MC9669 2007-04-27 2007-04-27 April 27, 2007 LICENSEE: Entergy Nuclear Operations, Inc. FACILITY: Pilgrim Nuclear Power Station SUBJECT: SUMMARY OF CONFERENCE CALLS ON APRIL 2, 2007, WITH ENTERGY NUCLEAR OPERATIONS, INC., REGARDING THE PILGRIM

* [2007-04-27] 1996 Water Sample from Torus Room Floor - Pilgrim. ML070440477 1996-03-20 6 05000293 96.0096.01 1996-03-20 2007-04-26 Extendon: 0 EWAl I I A T l n N Responsibla Manager: , . d.bY~w& Status: Operbf.co.+~ Division: PLANT Significance: 2 Depamnent: OPS Priority: A Sub Division: Doc TypeINum bec RPR Titie WATER SAMPLE FROM TORUS ROOM

* [2007-04-27] CR-PNP-2006-01914 - Pilgrim. ML070440479 2006-05-18 2 05000293 CR-PNP-2006-01914 2006-05-18 2007-04-26 L CONDITION REPORT Entergy I Originator: DyckmanJohn G Originator Phone: 786 1 CR-PNP-2006-01914 ' xiginator Group: Eng DE Mech Civil Struct Staff Supervisor Name: Pace,Raymond M Discovered Date: 05/18/2006

* [2007-04-27] GE-NE-0000-0066-0380-R1-NP, "Pilgrim Nuclear Power Station, Torsion Arm Clamp Stress Evaluation Report." ML071130384 2007-04-10 15 05000293 DPR-035 eDRF 0000-0064-9390 eDRF Section 0000-0066-7000-R0 GE-NE-0000-0066-0380-R1-NP 2007-04-10 2007-04-26 ML071080150+ w GE Energy, Nuclear General Electric Company 6705 Vallecitos Road Sunol. CA 94586 GE-N E-0000-0066-0380-Ri-N P eDRF Section 0

* [2007-04-27] Pilgrim - Repair of the Core Shroud Stabilizer Assemblies - Torsion Arm Clamp Stress Evaluation Report. ML071080222 2007-04-10 3 05000293 DPR-035 2.07.035 eDRF 0000-0064-9390 eDRF 0000-0066-7000-R0 TAC MD4918 GE-NE-0000-0066-0380-R1-NP 2007-04-10 2007-04-26 ML071080150+ Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. B

* [2007-04-27] Pilgrim, Main Stack Inspection Report - 05/08/2006. ML070440481 2006-05-08 19 05000293 2006-05-08 2007-04-26 9 knterrrv Main Stack Inspection Report 5/08/06 Inspection completed for: Entergy Pilgrim Nuclear Power Plant Rocky Hill Road Plymouth, MA 02360 5/08/06 ? Tower Service, inc. Inspection completed by: Broadcast Tower Service I

* [2007-04-27] Pilgrim, Procedure No. 3.M.5-2, Revision 10, "Main Stack Inspection Guideline." ML070440482 2006-06-30 22 05000293 3.M.5-2, Rev 10 2006-06-30 2007-04-26 . PILGRIM NUCLEAR POWER STATION Procedure No. 3.M.5-2 MAIN STACK INSPECTION GUIDELINE RTYPE H6.03 fl Review REFERENCEUSE 3.M.5-2 Rev. 10 REVISION 10 Paaes Affected 3,8,15-22 4 4,s 6 REVISION 9 Paaes Affected 5

* [2007-04-27] Interview Schedule - Region 1 Inspection. ML070440430 2006-10-06 2 05000293 2006-10-06 2007-04-26 YRC Inspector Paul Kaufman Suresh Chaudhary Shani Lewis John Richmond Dante Johnson Tim OÕHara Region I Inspection 9/18 -9/22 and 10/2 - 1016 2006 Interview Schedule ToDic - BWR FW Nozzle - BWR Stress Corrosion Cracking - HPC

* [2007-04-27] Pilgrim - Repair of the Core Shroud Stabilizer Assemblies - Torsion Arm Clamp Stress Evaluation Report. ML071080150 2007-04-26 ML071080222+ML071080224+ML071130384+ FNWEBNAVIGATE=1.0 SYSTEMTYPE=MEZZANINE DOCUMENTID=071080150 STARTPAGE=1 LIBRARYNAME=ml_adams^hqntad01

* [2007-04-26] IR 05000293-07-301; February 23, 2007 - March 1, 2007; Pilgrim Nuclear Power Station; Initial Operator Licensing Examination. ML071070491 2007-04-17 11 05000293 DPR-035 IR-07-301 2007-04-17 2007-04-25 April 17, 2007 Mr. Kevin Bronson Site Vice President Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 SUBJECT: PILGRIM NUCLEAR POWER STATION OPERATOR

April 21, 2007

New this week from NRC Public Document Room

* [2007-04-19] Condition Report CR-PNP-1997-01787, RFO-11 Erosion-Corrosion Data Review of Inspection Point #15 Found Instances of Wall Thickness Increases of Up to 0.227" When Comparing Previous Outage Results. ML070780380 1997-04-30 14 05000293 CR-PNP-1997-0187 1997-04-30 2007-04-18 Enteqgy CONDITION REPORT Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 0413011997 0O:OO CR-PNP-1997-01787 Originator Phone: 0 Operability Require

* [2007-04-19] Condition Report CR-PNP-1997-09135, Two Cracks Found in Core Spray Weld SW8BN. ML070780411 1997-02-23 4 05000293 CR-PNP-1997-09135 1997-02-23 2007-04-18 CONDITION REPORT I CR-PNP-I~~~-O~I~ Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 02/23/1997 0O:OO Originator Phone: 0 Operability Required: N R

* [2007-04-19] Condition Report CR-PNP-1999-09102, Loose Anchor Bolt Extensions. ML070780188 1999-03-26 2 05000293 CR-PNP-1999-09102 1999-03-26 2007-04-18 IÕ CONDITION REPORT 1 CR-PNP-1999-09102 Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 03/26/1999 0O:OO Originator Phone: o Operability Required:

* [2007-04-19] CR-PNP-----------, CR Just Entered, Operability of Refuel Bellows Seal Rupture Drain Leakage Alarm Switch. ML070780197 2006-03-08 1 05000293 2006-03-08 2007-04-18 3/s jus CR just entered states: An issue was raised during the Region I NRC Inspection for license renewal regarding the operability of FS-4803, Refuel Bellows Seal Rupture Drain leakage alarm switch. FS-4803 did not actuate

* [2007-04-19] CR-PNP-1990-01467, During Inspection of 2nd Pass FW-8 MT of Weld Revealed Indication 4" Long Crack- Like Linear. ML070780412 1999-06-01 3 05000293 CR-PNP-1999-01467 1999-06-01 2007-04-18 CONDITION REPORT I CR-PNP-1999-01467 Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 06/01/1999 0O:OO Originator Phone: 0 Operability Required: N

* [2007-04-19] CR-PNP-1990-09249, Torus Containment Shell One Area of Pitting Exceeding Acceptance Criteria of .066 Inches Base Depth. ML070780416 1999-05-22 4 05000293 CR-PNP-1999-09249 1999-05-22 2007-04-18 Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 05/22/1999 0O:OO Originator Phone: 0 Operability Required: N Reportability Required: N Initiated D

* [2007-04-19] CR-PNP-1996-00396, High Mitrate Levels Exists in the TBCCW System. ML070780367 1996-09-24 22 05000293 CR-PNP-1996-00396 1996-09-24 2007-04-18 EnteLqgy CONDITION REPORT CR-PNP-1996-00396 Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 09/24/1996 0O:OO Originator Phone: 0 Operability Requi

* [2007-04-19] CR-PNP-1996-09593, Crack in Housing for MO-1001-34A. ML070780372 1996-11-27 5 05000293 CR-PNP-1996-09593 1996-11-27 2007-04-18 ~ Entergy I CONDITION REPORT Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: I 1/27/1996 0O:OO CR-PNP-199609593 Originator Phone: 0 Operability Re

* [2007-04-19] CR-PNP-2000-09228, P-161C Suction Piping 98 Deg. Elbow for C Continuous SSW Hypo Pump Cracked and Leaking into Burm Area. ML070780418 2000-06-12 6 05000293 CR-PNP-2000-09228 2000-06-12 2007-04-18 ET?!tWg)f Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 06/12/2000 0O:OO CONDITION REPORT CR-PNP-2000-09228 Originator Phone: 0 Operability Requ

* [2007-04-19] CR-PNP-2001-02275, "A" SSW Discharge Piping 20 Foot Section of Rubber Lining Peeled off of Piping Exposing Bare Metal. ML070780431 2001-05-03 5 05000293 2001-05-03 2007-04-18 Erzfwgy I CONDITION REPORT Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 05/03/2001 0O:OO CR-PNP-2001-02275 Originator Phone: 0 Operability Required: N Reportabil

* [2007-04-19] CR-PNP-2001-04048, Received SBO DG Fuel Tank Leakage Alarm Alert Wet Probes. ML070780439 2001-09-10 4 05000293 CR-PNP-201-04048 2001-09-10 2007-04-18 I Enfwgy I CONDITION REPORT I C R - P N P - ~ O O ~ - O ~ O ~ ~ I Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 09/10/2001 0O:OO Originator Pho

* [2007-04-19] CR-PNP-2001-04171, Alarm C190-D3 SBO DG Fuel Tank Leakage in Alarm. ML070780453 2001-09-20 2 05000293 CR-PNP-2001-04171 2001-09-20 2007-04-18 I ErztHW I CONDITION REPORT I C R - P N P - ~ O O ~ - O ~ ~ ~ ~ I Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 09/20/2001 0O:OO Originator Phon

* [2007-04-19] CR-PNP-2001-04238, HCU 50-31 Leak. ML070780491 2001-09-27 4 05000293 CR-PNP-2001-04238 2001-09-27 2007-04-18 CONDITION REPORT CR-PNP-2001-04238 - En-zzY I ~ Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 09/27/200 1 0O:OO Originator Phone: 0 Operability

* [2007-04-19] CR-PNP-2001-04779, T- 112 Cation Regen Tank Found Second Leak. ML070780508 2001-11-08 4 05000293 CR-PNP-2001-04779 2001-11-08 2007-04-18 Enfffgy 1 CONDITION REPORT Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 11/08/2001 0O:OO CR-PNP-2001-04779 Originator Phone: 0 Operability Requ

* [2007-04-19] CR-PNP-2001-09403, Fire System has Broken Pipe Between 12-D-8, 12D-9 in AOG Building. ML070780529 2001-04-21 4 05000293 CR-PNP-2001-09403 2001-04-21 2007-04-18 Enfwgy 1 CONDITION REPORT Originator: CONVERTED DATA Originator Group: CONVERTED DATA Supervisor Name: CONVERTED DATA Discovered Date: 04/27/2001 0O:OO CR-PNP-2001-09403 1 Originator Phone: 0 Operability Req

* [2007-04-19] CR-PNP-2002-01411, Secondary Containment Leakrate Testing Was Aborted. ML070780615 2003-04-17 4 05000293 CR-PNP-2003-01411 2003-04-17 2007-04-18 Entergy CONDITION REPORT ~~~~~ Originator: Olson,Eric W Originator Group: Operations Mgmt Supervisor Name: DietrichSeter T Discovered Date: 04/17/2003 22: 12 CR-PNP-2003-01411 Originator Phone: 8477 Operabil

* [2007-04-19] CR-PNP-2002-01414, The Concrete Shield Block for the Drywell Equipment Hatch was Removed Prior to the Reactor Being Less than 212F. ML070780632 2003-04-19 18 05000293 CR-PNP-2003-01414 2003-04-19 2007-04-18 CONDITION REPORT I C R - P N P - ~ O O ~ - O ~ ~ ~ Originator: White,Thomas F Originator Group: Eng Design Mgmt Supervisor Name: BethayStephen J Discovered Date: 04/19/2003 18:lO Originator Phone: 7772 Opera

* [2007-04-19] CR-PNP-2002-09283, Unable to Reassemble E-122B, "B" TBCCW Heat Exchanger Head. ML070780545 2002-02-27 7 05000293 CR-PNP-2002-09283 2002-02-27 2007-04-18 + EnEet-gy I CONDITION REPORT Originator: Helms,Ralph E Originator Group: Maint Mechanical Mgmt Supervisor Name: T.Fox Discovered Date: 02/27/2002 01 :35 CR-PNP-2002-09283 Originator Phone: 8957 Operability

* [2007-04-19] CR-PNP-2002-10639, Received Blackout Diesel Generator Alarm (C3L-A4) Several Times During Shift on 06/19/2005. ML070780564 2002-06-19 3 05000293 CR-PNP-2002-10639 2002-06-19 2007-04-18 I Entwgy I CONDITION REPORT 1 CR-PNP-2002-10639 I Originator: Macdonald,John B Originator Group: Operations Staff Supervisor Name: England,Michael D Discovered Date: 06/19/2002 03:57 Originator Phone: 8 13

* [2007-04-19] CR-PNP-2002-12941, P-208D ("D Salt Service Water Pump) Shaft Had Pitting. ML070780603 2002-12-13 16 05000293 CR-PNP-2002-12941 2002-12-13 2007-04-18 Entwgy CONDITION REPORT ~ ~ ~~ ~ Originator: GaedtkeJoseph R Originator Group: Eng Sys Mech Staff Supervisor Name: LamoureuxJoseph R Discovered Date: 12/13/2002 16:35 CR-PNF-2002-12941 ~ ~ ~ Originator Phone

* [2007-04-19] CR-PNP-2003-01413, Secondary Containment Leakrate Testing was Aborted. ML070780624 2003-04-19 13 05000293 CR-PNP-2003-01413 2003-04-19 2007-04-18 .I Entefgy 1 CONDITION REPORT 1 C R - P N P - ~ O O ~ - O ~ ~ ~ 1 Originator: Olson,Erjc W Originator Group: Operations Mgmt Supervisor Name: Dietrich,Peter T Discovered Date: 04/19/2003 17:43 Originator Pho

* [2007-04-19] CR-PNP-2003-01471, Primary Containment Isolation Valve (PCIV) "262-F-013A" Experienced Increased but Acceptable Local Leak Rate Test Results. ML070780653 2003-04-22 3 05000293 CR-PNP-2003-01471 2003-04-22 2007-04-18 CONDITION REPORT I C R - P N P - ~ O O ~ - O ~ ~ ~ Originator: Felix,Andrew M Originator Phone: 8535 Originator Group: Eng P&C Code Program Staff Supervisor Name: Manderino,Peter Operability Required: N Repo

* [2007-04-19] CR-PNP-2003-01582, Primary Containment Isolation Valve (PCIV) "6-CK-62B Failed to Meet it's Individual Valve Local Leak Rate Test (LLRT) Acceptance Criteria. ML070790110 2003-04-25 12 05000293 CR-PNP-2003-01582 2003-04-25 2007-04-18 3 Originator: Manderino,Peter Originator Group: Eng P&C Components Mgmt Supervisor Name: Veglia,Vincenzo P Discovered Date: 04/25/2003 OR32 Entergy I CONDITION REPORT CR-PNP-2003-01582 Originator Phone: 8044

* [2007-04-19] CR-PNP-2003-02976, Pilgrim Construction Activity and Damage to Underground Utilities. ML070790183 2003-08-12 5 05000293 CR-PNP-2003-02976 2003-08-12 2007-04-18 c 1 ' I ADMIN Entergy I CR-PNP-2003-02976 Initiated Date: 8/12/2003 7:29 Owner Group :Eng Design Mgmt Current Contact: R. Hunnefeld Current Significance: C - CORRECTION Closed by: Buckley,Patricia A 1/30/200

* [2007-04-19] CR-PNP-2005-02621, Rollup CR with Various Problems Inservice Inspection Related. ML070790161 2005-05-16 9 05000293 CR-PNP-2005-02621 2005-05-16 2007-04-18 Entww 1 CONDITION REPORT Originator: Hickey,Christopher B Originator Group: QA Audit Staff Supervisor Name: Scannel1,Richard J Discovered Date: 05/16/2005 1555 CR-PNP-2005-02621 Originator Phone: 8454 Operab

* [2007-04-19] CR-PNP-2006-02799, Fair Amount of Water in Torus Room Floor. ML070790174 2006-07-26 3 05000293 CR-PNP-2006-02799 2006-07-26 2007-04-18 Entergy I CONDITION REPORT Originator: Gallant,Paul V Originator Group: Operations Staff Supervisor Name: Mcdonald,Michael L Discovered Date: 07/26/2006 2 1 :26 CR-PNP-2006-02799 Originator Phone: 8 132 Oper

* [2007-04-19] CR-PNP-2006-03467, Evidence of Past (Non-Active) Leakage Found on Torus Room Bay 1 Wall. ML070790156 2006-09-19 3 05000293 CR-PNP-2006-03467 2006-09-19 2007-04-18 CR- PNP-2006-03467 Condition Description: EVIDENCE OF PAST (NON-ACTIVE) LEAKAGE FOUND ON TORUS ROOM BAY 1 WALL BY NRC INSPECTORS DURING LICENSE REkEWAL WALkDOWN OF TORUS ROOM (SEE PHOTOS). Immediate Action D

* [2007-04-19] CR-PNP-2006-03468, A & B Aux Bay to Torus Loop Seal Piping (Secondary Containment Boundary Found with Heavy Corrosion). ML070790143 2006-09-19 2 05000293 CR-PNP-2006-03468 2006-09-19 2007-04-18 . CR-PNP-2006-03468 Condition Description: A & B AUX BAY TO TORUS LOOP SEAL PIPING (secondary containment boundary) FOUND WITH HEAVY CORROSION AT -I4 ft ELEV. BY NRC INSPECTORS DURING LICENSE REiEWAL WALKDOW

* [2007-04-19] CR-PNP-2006-03469, B Core Spray Suction Pipe Support H-14-1-8 in Torus Room Found to be Corroded. ML070790136 2006-09-19 4 05000293 CR-P NP-2006-03469 2006-09-19 2007-04-18 CR-P NP-2006-03469 Condition Description: B CORE SPRAY SUCTION PIPE SUPPORT H-14-1-8 IN TORUS ROOM BAY 11 FOUND WITH CORRODED BASEPLATE BY NRC INSPECTORS DURING LICENSE RENEWAL WALKDOWN OF TORUS ROOM (SEE P

* [2007-04-19] CR-PNP-2006-03479, Torus Anchor Bolt Baseplate Assemblies in Bays 9, 10, & 15 Found to be Corroded. ML070790130 2006-09-20 4 05000293 CR-PNP-2006-03479 2006-09-20 2007-04-18 Entefgy Originator: Pardee,Richard A Originator Phone: 8429 CONDITION REPORT CR-PNP-2006-03479 Originator Group: Eng P&C Code Program Staff Supervisor Name: Woods,Steven P Operability Required: Y Reportabili

* [2007-04-19] CR-PNP-2006-03497, During the NRC's Walkdown of the Torus Compartment as Part of License Renewal Review, the Inspectors Noted the Presence of Combustible Material... ML070780135 2006-09-21 4 05000293 ENN-DC-161 CR-PNP-2006-03497 2006-09-21 2007-04-18 CR-PNP-2006-03497 Condition Description: During the NRCÕs walkdown of the Torus Compartment as part of the License Renewal review, the inspectors noted the presence of combustible material. Fire P

* [2007-04-19] CR-PNP-2006-03677, Controls to Prevent and Monitor for Corrosion of the Drywell Shell Need to be Assessed and Strengthened. ML070790115 2006-10-04 1 05000293 CR-PNP-2006-03677 2006-10-04 2007-04-18 ErZtt?fgy 1 CONDITION REPORT ~ Originator: Ford,Bryan Seth Originator Group: Regulatory & Industry Affairs Mgmt Supervisor Name: Bethay,Stephen J Discovered Date: 10/04/2006 10: 10 CR-PNP-2006-03677 Originat

* [2007-04-19] CR-PNP-2006-03702, An Issue was Raised During the Region I Inspection for License Renewal Regarding the Expected Service Life of a Protective Coating for Buried Piping. ML070790120 2006-10-06 1 05000293 CR-PNP-2006-03702 2006-10-06 2007-04-18 i ri I I 1 CONDITION REPORT E n t w I CR-PNP-2006-03702 1 ~~ Originator: Anonymous Originator Group: CA&A Mgmt Supervisor Name: Mogolesko,Fred J Discovered Date: 10/06/2006 07: 17 Originator Phone: Operabili

* [2007-04-19] E-MAIL: (PD) Copy of LRA Amendment 15 letter - From Edward Sanchez to phb1@nrc.gov 3/13/07 12:29pm. ML071030042 2007-03-13 3 05000293 TAC MD3698 2007-03-13 2007-04-18 Page 1 of 1 Perry Buckberg - copy of LRA amendment 15 letter From: "Sanchez, Edward" To: Date: 3/13/2007 12:29 PM Subject: copy of LRA amendment 15 letter CC: "Lamoureux, Den

* [2007-04-19] E-MAIL: (PD) Dry Well - Event Number: 43245 - From Mary Lampert to Perry Buckberg 3/22/07 9:08am. ML071030069 2007-03-22 2 05000293 TAC MD3698 2007-03-22 2007-04-18 Page 1 of 1 Perry Buckberg - Dry Well - Event Number: 43245 From: "Mary Lampert" To: "Perry Buckberg(NRC PM)" Date: 3/22/2007 9:08 AM Subject: Dry Well - Event Number: 432

* [2007-04-19] E-MAIL: (PD) Fwd: Meeting Summary - March 14 & 15 2007 - From Perry Buckberg TO Doug Ellis 3/21/07 1:04pm ML071030063 2007-03-21 5 05000293 TAC MD3698 2007-03-21 2007-04-18 Page 1 of 1 Perry Buickberg - Fwd: Meeting Summary - March 14 & 15 2007 From: Perry Buckberg To: Doug Ellis Date: 3/21/2007 1:04 PM Subject: Fwd: Meeting Summary - March 14 & 15 2007 CC: Bryan Ford; Edward Sanchez;

* [2007-04-19] E-mail: (PD) Meeting Summary - March 14 & 15 2007 - From Perry Buckberg To Doug Ellis 3/19/07 7:05am. ML071030048 2007-03-19 4 05000293 TAC MD3698 2007-03-19 2007-04-18 Page 1 of 1 Perry Buckberg - Meeting Summary - March 14 & 15 2007 From: Perry Buckberg To: Doug Ellis Date: 3/19/2007 7:05 AM Subject: Meeting Summary - March 14 & 15 2007 CC: Robert Schaaf Doug, Please contact me

* [2007-04-19] E-MAIL: (PD) Pilgrim Draft ACRS Presentation - from Bryan Ford to Perry Buckberg 3/27/07 5:25pm. ML071030176 2007-03-27 3 05000293 TAC MD3698 2007-03-27 2007-04-18 Pilgrim Draft ACRS Presentation Page 1 of 1 Perry Buckberg - Pilgrim Draft ACRS Presentation From: "Ford, Bryan" To: "Perry Buckberg" , Date: 3/27/2007 5:25 PM Subj

* [2007-04-19] E-MAIL: (PD) Re: Draft Program Detail Pilgrim ACRS Subcommitte presentation.ppt. ML071020296 2007-03-28 7 05000293 TAC MD3698 2007-03-28 2007-04-18 Per begDafi Pilgrim ACRS Subcommittee presentation.ppt Pagel1 From: To: Date: Subject: "Ford, Bryan" "Perry Buckberg" 3/28/2007 12:49:13 PM Draft Program Detail Pilgrim ACRS Subc

* [2007-04-19] E-MAIL: (PD) Re: Drywell. ML071020291 2007-03-28 3 05000293 DPR-035 TAC MD3698 2007-03-28 2007-04-18 Page 1 of 1 Perry Buckberg - Drywell From: Perry Buckberg To: Glenn Meyer Date: 3/28/2007 1:51 PM Subject: Drywell Glenn, Related Amendments and my summary (of tangible actions) are attached. Perry file:/C:

* [2007-04-19] E-MAIL: (PD) Re: Entergy-Preliminary Durability Performance Evaluation of Perry. ML071020319 2007-03-29 13 05000293 TAC MD3698 2007-03-29 2007-04-18 PJerr B berg- FPW-: En-tergy-Preliminary Du-rabiliyPerformance Evaluation of Page] From: "Ford, Bryan" To: "Perry Buckberg" Date: 3/29/2007 12:09:58 PM Subject: FW: Entergy-Preli

* [2007-04-19] E-MAIL: (PD) Re: Final Presentation to Advisory Committee on Reactor Safguards. ML071020383 2007-03-30 3 05000293 TAC MD3698 2007-03-30 2007-04-18 Page 1 of 1 Perry Buckberg - Final Presentation to Advisory Committee on Reactor safeguards From: To: Date: Subject: CC: "Ford, Bryan" "Perry Buckberg" , 3/30/2007

* [2007-04-19] E-MAIL: (PD) Re: PDF copy of Entergy letter providing comments on draft SER on Pilgrim LRA. ML071020316 2007-03-29 17 05000293 TAC MD3698 2007-03-29 2007-04-18 Perry Buckberg - PDF copy of Entergy letter providing comments on draft SER on Pilgrim LRA From: "Sanchez, Edward" To: Date: 3/29/2007 9:49:47 AM Subject: PDF copy of Entergy

* [2007-04-19] E-MAIL: (PD) Re: People Attending ACRS Sub Committee Meeting. ML071020367 2007-03-30 3 05000293 TAC MD3698 2007-03-30 2007-04-18 Page 1 of 1 Perry Buckberg - FW: People Attending ACRS Sub Committee Meeting From: "Ford, Bryan" To: "Perry Buckberg" , Date: 3/30/2007 9:59 AM Subject: FW: People

* [2007-04-19] E-MAIL: (PD) Re: Pilgrim LR ACRS Subcommittee (SC) Meeting on 4/4/07 - From Mairtri Banerjee To Lambros Lois; Perry Buckberg 3/20/07 1:20pm. ML071030058 2007-03-20 2 05000219 05000293 TAC MD3698 2007-03-20 2007-04-18 i Perry Buckberg -_Re: Pilgrim LR ACRS Subcommittee (SC) Meeting on 4/4/07 Page 1l From: Maitri Banerjee To: Lambros Lois; Perry Buckberg Date: 3/20/2007 1:20:16 PM Subject: Re: Pilgrim LR ACRS Subcommitte

* [2007-04-19] E-MAIL: (PD) Re: Revised DRAFT ACRS Fluence Slides. ML071020343 2007-03-29 6 05000293 TAC MD3698 2007-03-29 2007-04-18 Page 1 of 1 Perry Buckberg - Fwd: Revised DARFT ACRS Fluence Slides From: Perry Buckberg To: Lambros Lois; Matthew Mitchell Date: 3/29/2007 7:31 AM Subject: Fwd: Revised DARFT ACRS Fluence Slides CC: Christopher Sy

* [2007-04-19] E-MAIL: (PD) Re: Revised DRAFT ACRS Fluence Slides2. ML071020345 2007-03-28 6 05000293 TAC MD3698 2007-03-28 2007-04-18 Page 1 of 1 Perry Buckberg - Revised DARFT ACRS Fluence Slides From: "Ford, Bryan" To: "Perry Buckberg" Date: 3/28/2007 4:28 PM t Subject: Revised DARFT ACRS Fluence Slides FYI

* [2007-04-19] E-MAIL: (PD) Request hard copy-safety evaluation report From Mary Lampert To- phb1@nrc.gov 3/5/07 11:32am. ML071030191 2007-03-05 2 05000293 TAC MD3698 2007-03-05 2007-04-18 Page 1 of 1 Perry Buckberg - request hard copy-safety evaluation report From: To: Date: Subject: "Mary Lampert" 3/5/2007 11:32 AM request hard copy-safety evaluation repor

* [2007-04-19] E-MAIL: (PD) Requested Document, Safety Evaluation Report With Open Items Related to the License Renewal of Pilgrim Nuclear Power Station. ML070750127 2007-03-01 678 05000293 TAC MD3698 2007-03-01 2007-04-18 Safety Evaluation Report With Open Items Related to the License Renewal of Pilgrim Nuclear Power Station Docket No. 50-293 Entergy Nuclear Operations U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Reg

* [2007-04-19] E-MAIL: (PD) Updated - Week of 2/26 conference call record From Perry Buckberg To Doug Ellis 3/7/07 6:36am. ML071030221 2007-03-07 10 05000293 TAC MD3698 2007-03-07 2007-04-18 Page 1 of I Perry Buckberg - Updated - week of 2/26 conference call record From: Perry Buckberg To: Doug Ellis Date: 3/7/2007 6:36 AM Subject: Updated - week of 2/26 conference call record CC: Robert Schaaf Doug, W

* [2007-04-19] E-MAIL: (PD) Week of 2/26 - Conference Calls From Perry Buckberg To Doug Ellis 3/6/07 9:18am. ML071030211 2007-03-06 5 05000293 DPR-035 TAC MD3698 2007-03-06 2007-04-18 Page 1 of I Perry Buckberg - Week of 2/26 - Conference Calls From: Perry Buckberg To: Doug Ellis Date: 3/6/2007 9:18 AM Subject: Week of 2/26 - Conference Calls CC: Bryan Ford; Robert Schaaf Doug, Please le

* [2007-04-19] ENN Engineering Standard, Rev. 0, IWE General Visual Containment Inspection. ML070790213 2004-03-08 18 05000293 ENN-EP-S-001, Rev 0 2004-03-08 2007-04-18 ENTERGY -llr ENN ENGf NEERING STANDARD ENN-EP-S-001 Rev. 0 Effective Date: 311 9/04 IWE General Visual Containment Inspection IP1 Applicable Site(s): IP2 IP3 IxI JAF IxI PNPS IXI VY Safety Related: X Yes N

* [2007-04-19] ENN-NDE-10.03, 02/02/06, VT-3 Examination. ML070790208 2006-02-02 27 05000293 ENN-NDE-10.03, Rev 1 2006-02-02 2007-04-18 i 1 Q U A l t N ~ T E D 1 ENN-NDE-10.03 REV. 1 i 1 INFOAMATIONAL~SE 1 NUCLEAR MANAGEMENT PAGE 1 OF27 1 t@??Y I I MANUAL i Approved: Title: VT-3 EXAMINATION (Print Name /?Title) t I (date) /g& - 17 , (Proc

* [2007-04-19] Listing of all Items NRC Region I Inspection of PNPS Various Pages Dated October 4 and 5, 2006 with Separate Pages for LR# 569 and LR# 536. ML070790188 2006-10-05 38 05000293 2006-10-05 2007-04-18 NRC Region Inspection of PNPS - All Hems Item Request Response Inspector Lead Category Update? 522 Provide any self assessments of the IS1 program or any related to the HPCl and IGSCC AMPs. None 523 Provide system or program

* [2007-04-19] PD_Email from Fred Mogolesko, Entergy, dtd 08/28/06 re: Preparation for Region I Inspection at Pilgrim. ML070660548 2006-08-28 2 05000293 2006-08-28 2007-04-18 From: "Mogolesko, Fred" To: "Glenn Meyer" Date: 08/28/2006 6:22:03 AM Subject: Preparation for Region I Inspection at Pilgrim We have some additional thoughts based on our di

* [2007-04-19] Pilgrim License Renewal Inspection Exit Meeting - Slides with Notes. ML070430476 2007-01-30 17 05000293 2007-01-30 2007-04-18 Pilgrim License Renewal Inspection Exit Meeting Nuclear Regulatory Commission Plymouth, MA January 30, 2007 Introductions Glenn Meyer, Team Leader NRC Participants Entergy Participants Meeting Purpose Present Inspection Resul

* [2007-04-19] PR 00.9228, Maintenance Discovered P-161C Suction Piping 98 deg. Elbow for C Continuous SSW Hypo Pump Cracked and Leaking in Burm Area, Closure Sheet ML070790547 2000-07-18 8 05000293 PR 00.9228 2000-07-18 2007-04-18 . 1 " ..,. - -. - 1 AITACHMENT12 1 L Sheet 1 of 1 RType G7.07 PROBLEM REPORT a Use of this fonn is not required. a- Closure Justification: Check one or more of the following and/or provide additional information as

* [2007-04-19] PR 01.2275, During Visual Exam of 'A' SSW Discharge Piping it was Discovered that a 20 Foot Section of Rubber Lining was Peeled Off of the Piping Exposing Bare Metal. ML070790568 2001-05-03 7 05000293 PR 01.2275 2001-05-03 2007-04-18 i 1 I ~ksure JuMicatbn: Check one or more of the forfawing andor provide additional information <,I L asmquired: Evaluation and conedive Action Complete I I See Evaluation Respome See ComxAive Action Respons

* [2007-04-19] PR 01.4048, Received SDO DG Fuel Tank Leakage Alarm Alert Wet Probes 1. ML070790583 2001-09-17 6 05000293 PR 01.4048 2001-09-17 2007-04-18 c I Pege 29 of 56 13 321 Rev 10 Page 33 of 50 .-._ ...- .- D

* [2007-04-19] PR 01.4171, Tour Operator Found Alarm C190-D3 on D# SBO DG Fuel Tank Leakage in Alarm. Panel Indicates Probe #1 Wet Alert Water Detected Alarm. ML070790596 2001-09-25 6 05000293 PR 01.4171 2001-09-25 2007-04-18 C W hom: sew To: Bubjm: 3 3, c- WA

* [2007-04-19] PR 01.4238, Tour Operator Reported that HCU 50-31 Leak Appears Worse - Closure. ML070790603 2001-10-10 6 05000293 PR 01.4238 2001-10-10 2007-04-18 -D 3 :CL I I I GfiW#a: P S O aQnmmC0: N ? .3.12? Rev. 10 -_- 3

* [2007-04-19] PR 01.940, Large Leak Reported in the Vicinity of AOG Building. Fire System has Broken Pipe Between 12-D-8 and 12-D-9. ML070790643 2001-04-27 9 05000293 PR 01.940 2001-04-27 2007-04-18 PROEILEM REPORT WPI J/ EF No Trend I Trending- 13121 Rev 0 Page 53 of 54 j 77th ' LARGE LEAK REPORTED 1N TXE VlNCtNKY Of AOG BUIlDING. FIRE SYSTEM HAS BROKEN PIPE c r, R D > d . ._ I.__ . . . . . . . . . . .

* [2007-04-19] PR 96.0396, High Nitrate Levels Exists in TBCCW System, High Nitrate Concentrations Have Been Associated with Stress Corrosion Cracking of Carbon Steel Piping. ML070790295 1998-07-13 55 05000293 PR 96.0396 1998-07-13 2007-04-18 -- -- ma ...- , 1 i i I j I i I i i I 1 I ! -. ,.e.-- ___ I 1. 2, 3:. 4, 5. 6. 7, 8 9. f 8. P e c c c* ,- e.- - .. +- . . ... . . -..-_ - . . I. c r: c- 2 7 P . .. 2 3 4, 1, Q": . rr 9. 3 4 ? p' i b V . I rr P D i

* [2007-04-19] PR 96.9593, Housing Crack on MO-1001-34A. ML070790326 1996-11-27 17 05000293 PR 96.9593 1996-11-27 2007-04-18 j . . 1 i PROBLEM REPORT I 1 Closed By: s t 1.3.121 Rev.0 Page6oof82 . .. Date: 11127196 Respanslbk Manager: HAUOYNA. R Dlutrlon: RRO Ooprrtnwnt: UCCOMP Sub Division: UCWSE Tale OURINO SHOP WORK ON THE OLD e 1OV HO

* [2007-04-19] PR 97.1787, RFO-11 Erosion Corrosion Data Review of Inspection Point #15. ML070790331 1997-05-01 12 05000293 PR 97.1787 1997-05-01 2007-04-18 , . . : . J s -- * . . .. c

* [2007-04-19] PR 97.9135, Cracks in Core Spray Weld SW8BN. ML070790338 1997-02-22 7 05000293 PR 97.9135 1997-02-22 2007-04-18 --JcJ - - - - - 'I AITACHMENT12 1 I Sheetlofl 1 RType G7 07 PROBLEM REPORT -I_- I Clokd By: Signature Date 1;. f- / , -- PR Data Entry CompletodCaptured. . e t r C & 1' / .cM g - 2 5 --71 Signature Date 1.3.121

* [2007-04-19] PR 99.1467, 2nd Pass FW-8 Revealed 4" Indication. ML070790530 1999-05-31 6 05000293 PR 99.1467 1999-05-31 2007-04-18 .3.121) Sheet 1 of 3 -. . i- ..I. ~ -.* J I

* [2007-04-19] PR 99.9102, 2" Dia. Torus Anchor Bolt Extensions at Torus Saddle Support Between Bays 12 and 13. ML070790535 1999-05-31 25 05000293 PR 99.9102 1999-05-31 2007-04-18 I ATTACHMENT12 1 I Sheet 1 of 1 I PROBLEM REPORT RType G7.07 __L -- a Trending . HPI (/* No Tmnd Closed By: PR Data Entry CornpktedlCaptured: PRELIMINARY EVALUAW CHECKLIST RTypt, ~9 02 2. CUSWICATION: 3, P

* [2007-04-19] Pre-Inspection Cover Sheet and Inspection Plan - Pilgrim Nuclear Generating Station; 05000293/2006007. ML070670370 2007-02-15 4 05000293 IR-06-007 2007-02-15 2007-04-18 PRE-INSPECTION COVER SHEET AND INSPECTION PLAN INSPECTORS: Lead: _Glenn Meyer_______ FACILITY: Pilgrim Nuclear Generating Station__________ Other:_Suresh Chaudhary________REPORT NO: 05000293/2006007 Dante Johnson Pa

* [2007-04-19] Procedure No. 2.1.8.7. Rev. 4, ASME Code Visual Examination of Primary Containment (RTYPE H6.02). ML070790647 2005-11-01 19 05000293 DPR-035 2005-11-01 2007-04-18 RNPE H6.02 PILGRIM NUCLEAR POWER STATION Procedure No. 2.1.8.7 ASME CODE VISUAL EXAMINATION OF PRIMARY CONTAINMENT A stop Think Act Review REFERENCE USE QUALITY RELATED 021 234 2.1.8.7 Rev. 4 REVISION 4

* [2007-04-19] Request for Additional Information on Time-Limited Aging Analyses for The Reactor Vessel and Internals, Pilgrim Nuclear Power Station, License Renewal Application (TAC No. MC9669). ML070810442 2007-03-15 3 05000293 TAC MC9669 2007-03-15 2007-04-18 March 15, 2007 MEMORANDUM TO: Louise A. Lund, Chief License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation FROM: Matthew A. Mitchell, Chief /RA/ Vessels and Internals Integrity Br

* [2007-04-19] RF014 ISI Summary Report for NRC Submittal with Attachment. ML070790228 2003-07-08 57 05000293 QA-03-024 2003-07-08 2007-04-18 OFFICE MEMORANDUPvl Pi@rim Jquckar Tower Station _- To: Bryan Ford Date: July 8, 2003 Dept. Dac. QA-03-024 Subject: RFOl4 IS1 SUMMARY REPORT FOR NRC SUBMITTAL : Distribution: R. Pardee C. Garrow S. Brennion V. lyer

March 3, 2007

Pilgrim license renewal application - NRC issues Safety Evaluation Report, with open items

The 678-page "Safety Evaluation Report With Open Items Related to the License Renewal of Pilgrim Nuclear Power Station", dated March 1, 2007, is available as ADAMS ACN ML070600798 (pdf - 2.3 MB). Here are the open items:
* NRC is unsure if the security diesel system is subject to AMR. If it is, Pilgrim needs to consider the components of this system in their application.
* Pilgrim needs to address how to manage the aging effect of inaccessible fire barrier penetration seals.
* Pilgrim needs to address how aging management would be impacted by potential corrosion in the inaccessible area of the Mark I steel containment drywell shell

* Pilgrim needs to improve on their current calculatations of reactor vessel neutron embrittlement TLAAs (time-limited aging analyses). The neutron fluence values presented in the application are unacceptable as is, due to the lack of benchmarking data in support of the plant-specific RAMA (Radiation Analysis Modeling Application) fluence calculations.

February 27, 2007

Massachusetts Attorney General is confused if it thinks it might still be a party to Pilgrim or VY license renewal case, sez NRC staff

In January 2006, the Massachusetts Attorney General (MassAG) filed petitions to intervene in license renewal proceedings for Pilgrim and Vermont Yankee. MassAG contended at the time that alleged new information about spent fuel pool fires should be considered in the proceedings. Both ASLBs rejected MassAG's contention, and NRC affirmed those decisions. MassAG wants NRC to reconsider and clarify that affirmation. NRC staff urges the Commission to make it clear to MassAG that the decision to affirm the ASLBs was final and will not be reconsidered. The NRC staff legal brief, dated February 16, 2007, is available as ADAMS ACN ML070510132.

January 24, 2007

150 attend NRC meetings on environmental review of Pilgrim license renewal application

In December, NRC released draft supplemental environmental impact statement on Pilgrim license renewal. Today, NRC held a pair of public meetings at a hotel in Plymouth to allow members of public to comment.

The summary also notes that NRC staff predicts the environmental impacts of continued operation "to be small, with the exception of some marine aquatic resources. Due to entrainment and impingement, the continued operation of the cooling water system would have moderate impacts on local winter flounder population, and the Jones River population of rainbow smelt, respectively. Continued operation of the cooling water system would have small to moderate impingement and entrainment impacts on other marine aquatic species as well." The summary also notes that "The impacts of alternatives (including the no-action alternative) were predicted to have impacts in at least some environmental aspects that could reach moderate or large significance."
[update (March 3, 2007): NRC project manager's meeting summary, including list of public attendees and accession numbers for transcripts and presentation slides, is available as ADAMS ACN ML070540205.]

Recent NRC inspections

* (released May 18) Pilgrim emergency preparedness report 50-293-2004-3

* (released Nov 25) Pilgrim operator exam report 50-293-2003-301

* (released Sept 23) Pilgrim fire protection report 50-293-2003-5

* (released Sept 16) Pilgrim safeguards report 50-293-2003-8

* Pilgrim report 50-293-2003-4

* Pilgrim problem ID baseline report 50-293-2003-3

* Pilgrim report 50-293/2002-7

* 2005-03-22: NRC to Discuss 2004 Performance Assessment for Pilgrim Nuclear Power Plant
NRC

March 12, 2004

Pilgrim gets extended National Guard protection

If not for a supplemental budget bill signed into law in Massachusetts, the National Guard would have ceased protecting Pilgrim nuclear plant on March 8. Senator Therese Murray, D-Plymouth, chairs the Senate Committee on Ways & Means: "Safety and security at Pilgrim Nuclear Power Plant, the Mirant Plant in Sandwich and PAVE PAWS have always been a priority of mine," she said. "Given today's uncertain times, we should continue to be proactive in safeguarding these installations. I am pleased that my colleagues in the House and Senate and the Governor sought to support my efforts to keep the Guard stationed at Pilgrim." Murray has been active on other Pilgrim security fronts, too. She worked with the United States Coast Guard in restricting ocean access to Pilgrim, the Federal Aviation Administration (FAA) to institute a no-fly zone over the plant, and pressed the Nuclear Regulatory Commission (NRC) to federalize security protecting Pilgrim. Murray also persuaded the Massachusetts Department of Public Health (DPH) to obtain Potassium Iodide from the NRC for all of the communities within the 10-mile Emergency Planning Zone and led efforts for legislation that provides the pills to all communities within a 50-mile radius of the plant.

[Source: Kingston Mariner (Massachusetts), "National Guard remains at nuclear plant", March 12, 2004]

November 6, 2003

Valve failure due to obstruction by loose fasteners for cartridge mounting plate

On February 22, 2003, at Pilgrim, the breaker for residual heat removal system valve MO-1001-29A tripped open on thermal overload when the valve was taken to the full open position for plant operation in shutdown cooling. Immediate actions were taken to investigate the cause of the failure, repair the motor operator and to restore the RHR loop to an operable status. Plant staff determined that the valve failed because four fasteners in the cartridge mounting plate backed out, which impacted the proper operation of the valve limit switches.

The plant performed a "weak link analysis" to determine the impact on valve MO-1011-29A, and to evaluate the event for reportability. Plant staff also reviewed the industry operating experience for the failure and took action to determine the extent of the condition in other safety related motor operated valves at Pilgrim. A list of potentially susceptible valves was developed and the valves were prioritized for inspection based on risk significance. Pilgrim inspected the valves during plant operations and during the refueling outage, and expanded the scope of the inspections as necessary depending on the inspection results. Although other cartridge plate and torque switch fasteners were found slightly loose (for example, by a 1/4 turn), none were significant enough to impact proper valve operation. The plant reviewed the industry standard maintenance practices for motor operated valves and enhanced the Pilgrim procedures to check the fasteners during preventive maintenance checks and to apply loctite on the fasteners to ensure they remain secure.

[Source: W. Raymond (Senior Resident Inspector, NRC) et al., Inspection at Pilgrim Nuclear Power Station conducted June 29, 2003 - September 27, 2003, Inspection Report 05000293/2003007, November 6, 2003]

November 7, 2003

Pilgrim requests relief from pressure test requirements for some small pipes in high rad area

Instead of hydrostatic testing, Pilgrim has proposed to substitute visual examinations of Reactor Coolant Pressure Boundary (RCPB) vent, drain and branch (VTDB) lines and connections for evidence of leakage every outage, and to check them during the 10-year ISI pressure test after four hours at pressure associated with 100% power. All the examinations would be conducted with the isolation valves in their normally-closed position. Plant Hatch was granted similar request in 1998. The proposed alternative will allow plant personnel to avoid an estimated one person-rem per outage, as the valve alignment and realignment required for the hydrostatic test would have to be performed in high radiation area near main steam loop piping within containment. The request also notes that, since the hydrostatic test would have to be performed after all RCPB maintenance is complete, it would always tend to occur at the end of an outage, and thus the time required to set up, test, and restore would impact outage schedule -- an unnecessary hardship pursuant to 10 CFR 50.55a(a)(3)(ii) without a sufficient compensating increases in the level of quality and safety. Entergy requests approval by December 1, 2004, to allow implementation during refueling outage 15.

[Source: William J. Riggs (Pilgrim Station - Director, Nuclear Assessment), letter to NRC, "Pilgrim Relief Request (PRR)-29, Relief from System Hydrostatic Test Requirements for Small Bore (² 1-inch), ASME Code Class 1 Reactor Coolant Pressure Boundary (RCPB) Vent, Drain and Branch (VTDB) Lines and Connections", November 7, 2003] Note: a PDF copy of the letter and Relief Request No. 29 is available from NRC at: http://www.nrc.gov/reading-rm/adams/web-based.html, by entering accession number ML033240525

September 27, 2003

Summary of Plant Status - June 29 - September 27, 2003 Pilgrim Nuclear Power Station operated during the period at 100 percent (%) core thermal power, except for short periods of operation at reduced power for routine condenser maintenance, testing and rod pattern adjustments. On September 6, 2003, while operating at 100% power, plant power decreased to approximately 35% due to the trip of the A reactor recirculation pump following the loss of 480 volt bus B-1and its associated loads at 11:51 a.m. Power to Bus B1 was restored at 11:51 p.m. on September 6, and the A recirculation pump was restarted at 9:07 a.m. on September 7. The plant resumed operation at full power at 11:20 p.m. on September 7.

[Source: W. Raymond (Senior Resident Inspector, NRC) et al., Inspection at Pilgrim Nuclear Power Station conducted June 29, 2003 - September 27, 2003, Inspection Report 05000293/2003007, November 6, 2003]



(c) 2003 - 2011 nuclear.com. All rights reserved.