Clinton FAQs
* The cost to build the 1,043-megawatt Clinton power plant, which came online in 1987, was $4.25 billion. The reactor can meet the electricity needs of about 1 million homes, according to Exelon. [Source: Crain's Chicago Business, "Exelon site gets early permit for new nuclear plant", March 8, 2007] NRC has a
performance indicator and inspection finding matrix webpage for Clinton.
|
Clinton news
February 8, 2008 Clinton - Plant Mgr Russ Kearney promoted to Site VP Exelon expects the following promotions to take place over the next couple of weeks: * Site Vice President, Clinton, Brian Hanson was named Site Vice President, Braidwood * Plant Manager, Clinton, Russ Kearney will be promoted to Site Vice President, Clinton * Mark Kanavos, a former Plant Manager at Comanche Peak, was named Plant Manager, Clinton [Source: NRC Region III, "Exelon Nuclear announces Executive Realignment", Morning Report, February 7, 2008 -- ACN ML080380472] June 23, 2007 New this week from NRC Public Document Room * [2007-06-23] Clinton - Commitment for Hydrogen Igniter Backup Power Supply and Closure Process for Generic Issue 189, "Susceptibility of Ice Condenser and Mark III Containments to Early Failure from Hydrogen Combustion During a Severe Accident." ML071510562 2007-06-15 4 05000461 NPF-062 GSI-189 2007-06-15 2007-06-22 June 15, 2007 Mr. Christopher M. Crane President and Chief Nuclear Officer AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555 SUBJECT: CLINTON POWER STATION, UNIT NO. 1 - COMMITMENT FOR HYDRO * [2007-06-20] Ltr 06/12/07 Clinton Re Confirmation of Initial/Requalification Operator License Examinations ML071650404 2007-06-12 3 05000461 NPF-062 U-603810 2007-06-12 2007-06-19 June 12, 2007 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 SUBJECT: CLINTON POWER STATION CONFIRMATION OF June 16, 2007 New this week from NRC Public Document Room * [2007-06-16] Clinton Power Station, Unit 1, Supplement to Request for Amendment to Technical Specification 3.3.1.1, "Reactor Protection System (RPS) Instrumentation," Scram Discharge Volume Level Instrumentation Surveillance Requirements ML071580953 2007-06-06 10 05000461 NPF-062 RS-07-086 2007-06-06 2007-06-15 AmerGen Energy Company, LLC wwwexeloncorp.com 4300 Winfield Road Warrenville, IL 6o555 RS-07-086 June 06, 2007 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Clinton P * [2007-06-15] Clinton, Scheduling of Operator Licensing Examination ML071570370 2007-05-29 1 05000461 NPF-062 U-603810 2007-05-29 2007-06-14 AmerSnM An Exelon Company Clinton Power Station R. R. 3, Box 228 Clinton, IL 61727 U-603810 May 29, 2007 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-001 Clinton Power June 2, 2007 New this week from NRC Public Document Room * [2007-06-02] Clinton, Unit 1 - Issuance of License Amendment 176 regarding Technical Specification Surveillance Requirement 3.4.6.1 ML071160306 2007-06-01 ML071160294+ ML071510253+ FNWEBNAVIGATE=1.0 SYSTEMTYPE=MEZZANINE DOCUMENTID=071160306 STARTPAGE=1 LIBRARYNAME= ML_adams^hqntad01 * [2007-05-31] Enclosure 2 - R. Grubb Ltr re: Certificate of Compliance No. 9233, Rev. 8, for the Model No. TN-RAM Package ML071310208 2007-05-07 4 07109233 TAC L24081 2007-05-07 2007-05-30 ML071280653+ LIST OF USERS FOR CERTIFICATE - 9233 FOR MODEL - TN-RAM AMERGEN ENERGY COMPANY, LLC ATTN: MR. W. S. ILIFF CLINTON PWR STATION R.R.3, BOX 228 CLINTON IL 61727 AMERGEN ENERGY COMPANY, LLC ATTN: MR. TONY Early Site Permit-related June 30, 2007 New this week from NRC Public Document Room * [2007-06-15] 2006/10/24-Limited Appearance Statement of David A. Kraft ML062980122 2006-10-24 3 05200007 52-007-ESP ASLBP 04-821-01-ESP RAS 12415 2006-10-24 2007-06-14 2006-10-24 lHearingDockeqt- Request to make ora statement atClinton EIS hearing-P Page 1 i1 From: To: Date: Subject: Dave Kraft , * [2007-06-15] 2006/10/25-Limited Appearance Statement of Kathy Barnes ML062990473 2006-10-25 3 05200007 52-007-ESP ASLBP 04-821-01-ESP RAS 12422 2006-10-25 2007-06-14 2006-10-26 -1D A5 / Rà V HearingDocket - Statement re: Clinton reactor Early Site Permit EIS From: "Kathy Barnes" To: , , * [2007-06-13] 04/01/05-Fourth Additional Disclosures of Intervenors Environmental Law and Policy Center, Blue Ridge Environmental Defense League, Nuclear Information and Resource Service, Nuclear Energy Information Service, and Public Citizen ML051080053 2005-04-01 7 05200007 +reviewednvg 52-007-ESP ASLBP 04-821-01-ESP RAS 9848 2005-04-01 2007-06-12 2005-04-04 cjgtj~ PELATE CORMESPQORDs&5 DOCKETED USNRC UNITED STATES OF AMERICA April 4, 2005 (7:26am) NUCLEAR REGULATORY COMMISSION OFFICE OF SECRETARY RULEMAKINGS AND BEF * [2007-06-13] 2004/06/10-E-mail from Diane Curran to Board and Parties informing that petitioners did not file a separate reply to Exelon's and the NRC Staff's responses to their contentions regarding Exelon's ESP application ML060480391 2004-06-10 1 05200007 52-007-ESP ASLBP 04-821-01-ESP RAS 8008 2004-06-10 2007-06-12 2004-06-10 [ ~ e a r i n ~ ~ o c k e t - Clarification regarding filing in Clinton ESP case Page 1 1 From: Diane Curran cdcurran @ harmoncurran.com> To: "G. Paul Bollwerk, Ill" June 2, 2007 New this week from NRC Public Document Room * [2007-06-02] Clinton, Unit 1 - Issuance of License Amendment 176 regarding Technical Specification Surveillance Requirement 3.4.6.1 ML071160294 2007-05-24 9 05000461 NPF-062 TAC MD2474 2007-05-24 2007-06-01 ML071160306+ May 24, 2007 Mr. Christopher M. Crane President and Chief Executive Officer AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, Illinois 60555 SUBJECT: CLINTON POWER STATION, UNIT NO. 1 * [2007-06-02] Clinton, Unit 1 - Tech Spec Page for Amendment 176 regarding Technical Specification Surveillance Requirement 3.4.6.1 ML071510253 2007-05-24 1 05000461 NPF-062 TAC MD2474 2007-05-24 2007-06-01 ML071160306+ RCS PIV Leakage 3.4.6 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.6.1 ------------------- NOTE-------------------- Not required to be performed in MODE 3. Verify equivalent leakage * [2007-05-31] LER 07-002-00 for Clinton, Unit 1 Regarding Improper Installation of Stanchions in Containment Pool Swell Zone ML071410186 2007-05-10 4 05000461 NPF-062 U-603817 LER 07-002-00 2007-05-10 2007-05-30 AmerGen An Exelon Company Clinton Power Station R. R. 3, Box 228 Clinton, IL 61727 1 OCFR50.73 U-603817 May 10, 2007 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D May 26, 2007 New this week from NRC Public Document Room * [2007-05-25] Clinton Power Station, Unit 1 - Administrative Change To Facility Operating License in Conjunction with the Commission Order EA-06-037 (TAC MD2210) ML071430437 2007-05-16 5 05000461 NPF-062 EA-06-037 TAC MD2210 2007-05-16 2007-05-24 Orr IL C ,JY- . iLTIIlr.A~l ~ 4 PA UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 16, 2007 Mr. Christopher M. Crane, President and Chief Nuclear Officer AmerGen Energ May 19, 2007 New this week from NRC Public Document Room * [2007-05-19] 05/09/2007 Summary of Public Meeting with Exelon Generation Company, LLC Regarding Clinton End-of-Cycle Plant Performance Assessment for the period of January 1, 2006, through December 31, 2006. ML071360187 2007-05-14 6 05000461 NPF-062 2007-05-14 2007-05-18 May 14, 2007 LICENSEE: Exelon Generation Company, LLC FACILITY: Clinton Power Station SUBJECT: SUMMARY OF THE MAY 9, 2007, PUBLIC MEETING TO DISCUSS THE CLINTON END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On May 9, 2007 * [2007-05-18] FOIA/PA-2007-0187 - Resp 1 - Final. ML071290137 2007-05-04 2 05000461 FOIA/PA-2007-0187 2007-05-04 2007-05-17 ML071290133+ NRC FORM 464 Part I U.S. NUCLEAR REGULATORY COMMISSION FOIA/PA RESPONSE NUMBER (6-1998) 2007-0187 1 0* RESPONSE TO FREEDOM OF , INFORMATION ACT (FOIA) / PRIVACY RESPONSE ! FINAL PARTIAL 4 ACT (P * [2007-05-17] Clinton, Unit 1 - Annual Radiological Environmental Operating Report. ML071280382 2007-04-27 128 05000461 NPF-062 U-603816 2007-04-27 2007-05-16 Amer ¨ sm An Exelon Company Clinton Power Station R. R. 3, Box 228 Clinton, IL 61727 April 27,2007 U-603816 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Clinton P * [2007-05-17] Clinton, Unit 1 - Submittal of the 2006 Annual Radioactive Effluent Release Report. ML071280252 2007-04-27 81 05000461 NPF-062 U-603815 2007-04-27 2007-05-16 AmerG ¨ An Exelon Company Clinton Power Station R. R. 3, Box 228 Clinton, IL 61727 1 OCFR50.36a U-603815 April 27, 2007 Document Control Desk Nuclear Regulatory Commission Washington, D.C. 20555 Clinton Power * [2007-05-16] Clinton EOC Meeting Slides, Annual Assessment Meeting, Reactor Oversight Program - CY 2006. ML071310085 2007-05-09 24 05000461 2007-05-09 2007-05-15 Clinton Station Annual Assessment Meeting Reactor Oversight Program - CY 2006 Nuclear Regulatory Commission - Region III Clinton, IL May 9, 2007 2 Purpose of TodayÕs Meeting ¥ A public forum for discussion of the licenseeÕs p * [2007-05-15] 03/02/2007 Clinton Power Station EOC Annual Assessment Letter (Report 05000461-07-001). ML070610156 2007-03-02 7 2007-03-02 2007-05-14 * [2007-05-15] 05/09/2007, Notice of Meeting Clinton EOC and NRC to Discuss NRC End-of-cycle Assessment of Clinton Power Station Performance for the 2006 Calendar Year. ML070930532 2007-04-02 3 2007-04-02 2007-05-14 * [2007-05-15] Clinton, Unit 1 - Relocation of the Technical Support Center. ML070540270 2007-03-12 9 2007-03-12 2007-05-14 * [2007-05-15] Clinton, Unit 1, Introduction of Lead Use Channels. ML070580431 2007-02-27 6 2007-02-27 2007-05-14 * [2007-05-15] Clinton, Unit 1, Reply to Notice of Violation: EA-06-291. ML070680325 2007-03-09 6 2007-03-09 2007-05-14 * [2007-05-15] FOIA/PA-2007-0014 - Sen. Hillary Rodham Clinton, correspondence log between her office & NRC, from Jan. 1, 2001 to present ML062850436 2006-10-03 1 2006-10-03 2007-05-14 ML070660592+ * [2007-05-15] FOIA/PA-2007-0093 - Correspondence from January 2002 to present, to and from Senators McCain, Clinton, Obama, Dodd, Biden, Brownback, Hagel, named former Senators, Representatives, mayors and governors ML070250126 2007-01-24 2 2007-01-24 2007-05-14 * [2007-05-15] Issuance of Early Site Permit for Exelon Generation Company, LLC, Clinton Site. ML070670140 2007-03-15 85 2007-03-15 2007-05-14 * [2007-05-15] M070308A-Affirmation Session: I. SECY-07-0034 - Exelon Generation Company, LLC (Early Site Permit for Clinton ESP). ML070670244 2007-03-08 4 2007-03-08 2007-05-14 * [2007-05-15] Press Release-07-035 - NRC Issues First-Ever Early Site Permit for Clinton Site in Illinois. ML070740727 2007-03-15 2 2007-03-15 2007-05-14 * [2007-05-15] SRM-M070308A - Affirmation Session: I. SECY-07-0034 - Exelon Generation Company, LLC (Early Site Permit for Clinton ESP) ML070670189 2007-03-08 1 2007-03-08 2007-05-14 May 12, 2007 New this week from NRC Public Document Room * [2007-05-11] FOIA/PA-2007-0187 - Clinton's emergency plan, two letters from utility dated June 30, 2006 & December 19, 2006, re: NRC's safety evaluation ML071160396 2007-04-26 1 FOIA/PA-2007-0187 2007-04-26 2007-05-10 Page 1 of 1 FOIA - Request for two documents From: "Chapman, Nancy" To: Date: 04/26/2007 1:00 PM Subject: Request for two documents Re: Clinton Power Station - Docket No. 50461 T * [2007-05-10] Clinton, Unit 1, Withdrawal of Request for Amendment to Technical Specification 3.6.5.1, "Drywell" and 5.5.13, "Primary Containment Leakage Rate Testing Program." ML071210469 2007-04-30 2 05000461 NPF-062 RS-07-075 2007-04-30 2007-05-09 AmerGen Energy Company, LLC www.exeloncoi p.com 4300 Winfield Road Warrenville, 11 . 6o555 RS-07-075 April 30, 2007 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 * [2007-05-08] IR 05000461-07-007, on 03/05/2007 - 03/23/2007; Clinton Power Station; Identification and Resolution of Problems. ML071220208 2007-05-01 27 05000461 NPF-062 IR-07-007 2007-05-01 2007-05-07 May 1, 2007 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 SUBJECT: CLINTON POWER STATION NRC PROBLEM IDEN May 5, 2007 New this week from NRC Public Document Room * [2007-05-05] Clinton, Unit 1 - Request for NRC Approval of Changes to the Plant Emergency Plan Annex. ML061920575 2006-06-30 18 05000461 NPF-062 EP-AA-1003 EP-AA-120-1001, Rev 4 RS-06-080 2006-06-30 2007-05-04 AmerGens AmerGen Energy Company, LLC www.exeloncorp.com An Exelon Company 4300 Winfield Road Warrenville, I L 60555 10 CFR 50.54(q) RS-06-080 June 30, 2006 U. S. Nuclear Regu * [2007-05-05] Clinton, Unit 1, Additional Information Supporting Request for NRC Approval of Changes to Clinton Power Station Emergency Plan Annex. ML063530752 2006-12-19 14 05000461 NPF-062 RS-06-185 2006-12-19 2007-05-04 AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, (L 60555 RS-06-185 December 19, 2006 Subject: References: (1) www,exeloncorp .com U. S. Nuclear Regulatory Commission ATTN: Document Control Desk W * [2007-05-05] Press Release-III-07-018 - NRC to Discuss 2006 Performance Assessment for Clinton Nuclear Power Plant. ML071240162 2007-05-04 2 05000461 Press Release-III-07-018 2007-05-04 2007-05-04 NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION 2443 Warrenville Road Lisle IL 60532 Web Site: http://www.nrc.gov E-mail: opa3@nrc.gov No. III-07-018 May 4, 2007 CONTACT: Viktoria Mitlyng (630) 829-9662 N * [2007-05-03] Ltr. 04/25/07 Clinton Re: Initial License Examination Notification. ML071210232 2007-04-25 5 05000461 NPF-062 2007-04-25 2007-05-02 April 25, 2007 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Dear Mr. Crane: In a telephone conversation on April 9 * [2007-05-03] U.S. Dept of Homeland Security/Revision to the Illinois Plan for Radiological Accidents (IPRA) Volume VIII-Clinton dated 09/07/Letter. ML071150026 2007-04-24 1 05000461 2007-04-24 2007-05-02 Homeland Security April 24,2007 Mr. Roland Lickus Chief, State & Government Affairs U.S. NRC Region 111 2443 Warrenville Road, Suite 210 Lisle, Illinois 60532-4352 Dear Mr. Lickus: Attached is the revision to the Illinois Pla * [2007-05-01] Clinton, Unit 1 - Updated Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors from November 4, 2005 through November 3, 2006. ML071100413 2007-04-19 7 05000461 NPF-062 RS-07-068 2007-04-19 2007-04-30 www.exe1oncorp corn AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555 April 19, 2007 An Exelon Company 10 CFR 50.46 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washingt April 28, 2007 New this week from NRC Public Document Room * [2007-04-28] IR 05000461-07-002; AmerGen Energy Company LLC; 01/01/52007 - 03/31/2007; Clinton Power Station; Event Followup. ML071100080 2007-04-19 28 05000461 NPF-062 IR-07-002 2007-04-19 2007-04-27 April 19, 2007 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 SUBJECT: CLINTON POWER STATION NRC INTEGRATE * [2007-04-26] LER 07-001-00 for Clinton, Unit 1, Regarding Inadequate Consideration of Vortexing in Design Calculations. ML071070294 2007-04-06 4 05000461 NPF-062 U-603811 LER 07-001-00 2007-04-06 2007-04-25 AmerO aM An Exelon Company Clinton Power Station R. R. 3, Box 228 Clinton, IL 61727 10 CFR 50.73 U-603811 April 6, 2007 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington March 8, 2007 *
NRC Votes to Approve Early Site Permit for Clinton Site | Exelon has no plan to build a new nuclear plant at location in near future
The Nuclear Regulatory Commission today voted to approve an Early Site Permit (ESP) for Exelon Generation Company, LLC. The ESP resolves with finality certain environmental, site suitability and emergency planning issues with regard to the possible construction and operation of a new nuclear plant next to the Clinton Power Station in Clinton, Ill. The next step in NRC's permit process is for NRC staff to actually issue the permit, which must occur within 10 days of the commission's vote. Exelon was the first to apply for an ESP, and will be the first company to receive an early site permit under the never before used licensing process. Exelon has not decided to move forward with building a new nuclear plant. "Certain conditions would have to fall into place before Exelon would consider building a plant: a workable solution to the spent fuel disposal problem; community acceptance; the right reactor technology; and the economics must be favorable," said Marilyn Kray, Exelon Nuclear Vice President. The 20-year permit allows Exelon to "bank" a site for a possible power plant; however, it does not authorize construction of a new plant. Should the company decide to build a power plant, it would need to apply for a combined operating license. *
U.S. OKs early site permit for nuclear power plant
Exelon Corp., which sought the agency's first-ever early site permit in September 2003, would have up to 20 years to seek a license from the NRC to build and operate a reactor at the company's Clinton, Illinois, site, where it already has one nuclear reactor generating electricity. The decision is a step toward the Bush administration's goal to expand nuclear power to meet growing U.S. electricity demand. It would take the NRC about 24 months to review and approve any Exelon request to construct a new reactor at the Clinton location, an agency spokesman said. *
Clinton nuclear plant wins permit -- losses assessment
... the DeWitt County Review Board has decided against lowering the assessment for the Clinton Nuclear Plant for taxing purposes. Exelon, AmerGen's parent company, appealed the Supervisor of Assessments $1.1 billion assessment for taxes that'll be paid next year. Corporate executives complained specifically about a $200 million value put on a permit application for a plant expansion. The Review Board deliberated for one hour before deciding to keep the assessment at the level that would raise Exelon's property tax bill for the plant to $8.5 million -- a 66 percent, one-year increase. The Nuclear Regulatory Commission today approved issuing that early site permit. So, AmerGen has won one and lost one today. Recent NRC inspections * (released May 15) Clinton problem ID and resolution team report 50-461-2004-3 * (released Feb 21) Clinton report 50-461-2003-9 * (released Dec 23) Clinton 4160V electrical system and shutdown service water system report 50-461-2003-7 * Clinton report 50-461-2003-3 * Clinton operator qual report 50-461-2003-2 * Clinton report 50-461-2002-10 * Clinton report 50-461/2002-9 January 7, 2005 Exelon announcement of management personnel changes: * Mike Pacillio to be promoted to Senior Vice President for Midwest Operations responsible for Braidwood, Byron, Clinton, Dresden, LaSalle, Quad Cities and Zion stations March 23, 2004 * Clinton - reactor scram from 93% power due to generator overvoltage trip March 5, 2004 * Clinton - fish kill (several hundred shad) when shut down for refueling October 15, 2003, 2003 * The Clinton early site permit application is available electronically at: http://www.nrc.gov/reading-rm/adams/web-based.html -- enter ML032721596 as the search term. September 25, 2003 First applications filed for Early Site Permits - Clinton, North Anna No permits for new nuclear power stations have been issued in the United States since the Three Mile Island accident in 1979. But today, Exelon and Dominion filed applications requesting NRC approval for construction of a standardized design plant at their Clinton (Exelon) and North Anna (Dominion) sites. NRC's application review process is expected to take about 33 months. Each utility would then have twenty years (renewable to forty) to decide on and build a new plant at their site. The utilities have not decided if or when or what to build if their permit is approved. The USDOE contributed towards the cost of preparing the applications. [Refs: Exelon press release, "Exelon Is the First to File an Early Site Permit Application With NRC", September 25, 2003 2:45 pm ET; and Reuters, "Utilities seek permits for possible nuke projects", September 25, 2003 6:13 pm ET] September 4, 2003 9th refueling scheduled The next refueling outage (CIR09) is scheduled to begin on February 3, 2004. It is scheduled to last eighteen days. [Ref: Amergen letter to NRC, "August 2003 Monthly Operating Report", dated September 4, 2003] July 21, 2003 June 15, 2003 |